# Project calendar

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Working time rules of a project](https://pmdecoder.com/en/concept/working-time-rules-of-a-project/)
- Topic area: [Scheduling](https://pmdecoder.com/en/area/scheduling/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/project-calendar/

## Definition

The project calendar determines the working time a schedule calculates with: working days and non-working days, daily working hours, public holidays, company holidays and special periods such as shift operation or possession periods. Planning tools use it to calculate dates from durations. An activity with a duration of five days ends on different days depending on the calendar.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Project calendar](https://pmdecoder.com/en/glossary/project-calendar-pmi/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The project calendar applies to the whole project; resource calendars record the availability of individual people or machines, such as leave or part-time work. Activity calendars govern exceptions for individual activities, such as work that is only possible at weekends. An appointment diary in everyday office life, by contrast, manages meetings and has nothing to do with calculating dates.

## In practice

A project to renew a railway track may only work during night-time possessions and on two extended weekends. The planner creates a separate calendar for this in which only these time windows count as working time. With the normal office calendar, the planning tool would have calculated completion after six weeks; with the possession calendar, the result is a realistic four months. In addition, the installation crews enter their holidays in resource calendars.

## Frequently asked questions

### Which public holidays apply in the project calendar?

Those that apply at the respective work locations. Projects spanning several federal states or countries often need several calendars.

### Can a project have several calendars?

Yes. A standard calendar for the project is usual, supplemented by resource and activity calendars for exceptions.

## Related terms

- [Project schedule](https://pmdecoder.com/en/glossary/project-schedule/)
- [Activity duration](https://pmdecoder.com/en/glossary/activity-duration/)
- [Activity](https://pmdecoder.com/en/glossary/activity/)

---