# Project calendar

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Working time rules of a project](https://pmdecoder.com/en/concept/working-time-rules-of-a-project/)
- Topic area: [Scheduling](https://pmdecoder.com/en/area/scheduling/)
- Canonical version: https://pmdecoder.com/en/glossary/project-calendar-pmi/

## Definition

In PMI usage, the project calendar is a calendar showing on which working days and in which shifts scheduled activities can take place. It distinguishes working time from non-working time such as weekends, public holidays or company shutdowns. The schedule model uses this calendar to convert durations into specific start and finish dates. In addition, resource calendars can reflect the availability of individual people or equipment, and different calendars can apply to particular activities, for example work carried out in shifts.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Project calendar](https://pmdecoder.com/en/glossary/project-calendar/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The cross-framework project calendar refers to the same thing; this entry gives the PMI view. A resource calendar applies only to one resource, for example with leave or part-time work, whereas the project calendar applies to the project as a whole. The project schedule contains the dates, the project calendar only the rules by which they are calculated.

## In practice

An internationally distributed software project works with teams in Germany and India. The project calendar sets a five-day week; each team has its own calendar with its public holidays. Because the teams have different holidays, the planning tool automatically moves a handover by two days when an Indian public holiday falls within the planned period.

## Frequently asked questions

### Why does a project need its own calendar?

Because durations are estimated in work periods. Without defined working days and shifts, they cannot be converted into dates reliably, and public holidays or shutdowns would be overlooked.

### What happens when the calendar changes?

All affected dates move. If, for example, an additional Saturday is scheduled as a working day, subsequent activities move forward. Such changes should therefore be made deliberately and documented.

## Related terms

- [Project calendar](https://pmdecoder.com/en/glossary/project-calendar/)
- [Duration](https://pmdecoder.com/en/glossary/duration/)
- [Project schedule](https://pmdecoder.com/en/glossary/project-schedule-pmi/)
- [Resource planning](https://pmdecoder.com/en/glossary/resource-planning/)
- [Activity duration](https://pmdecoder.com/en/glossary/activity-duration/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.