# Project budget

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Approved funds of a project](https://pmdecoder.com/en/concept/approved-funds-of-a-project/)
- Topic area: [Cost and economic viability](https://pmdecoder.com/en/area/cost-and-economic-viability/)
- Canonical version: https://pmdecoder.com/en/glossary/project-budget-pmi/

## Definition

In PMI usage, the project budget comprises all funds approved for carrying out the project. It is built up in layers: the cost estimates of the work packages, together with the contingency reserves for identified risks, form the cost baseline, which serves as the reference for performance measurement. On top of this comes the management reserve for unforeseen work within scope; it is part of the budget but not of the cost baseline. The budget is spread over the project duration, which yields the planned cash outflow. Changes to the budget go through change control, and access to the management reserve usually requires approval from someone outside the project management.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Project budget](https://pmdecoder.com/en/glossary/project-budget/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The project budget corresponds to the cross-framework term project budget; PMI places particular emphasis on the layering into cost baseline and management reserve. Budget at completion is narrower and denotes the sum of all budgets in the performance measurement baseline without the management reserve. Cost estimates are forecasts, whereas the budget is approved.

## In practice

For the conversion of a warehouse, the cost estimates of the work packages add up to 2.1 million euros. The risk analysis yields a contingency reserve of 180,000 euros, bringing the cost baseline to 2.28 million euros. Management additionally approves a management reserve of 120,000 euros, giving a project budget of 2.4 million euros. The steering committee decides on the use of the management reserve.

## Frequently asked questions

### Why is the management reserve part of the budget but not of the cost baseline?

Because it is intended for work that nobody could foresee during planning. It cannot be assigned to any work package and would distort performance measurement. Only when it is released does the amount move into the cost baseline.

### Who approves the project budget?

Usually the sponsor or a body with budget responsibility. Who exactly is responsible, and which amounts the project manager may release, is set by the organization’s governance rules.

## Related terms

- [Project budget](https://pmdecoder.com/en/glossary/project-budget/)
- [Budget at completion](https://pmdecoder.com/en/glossary/budget-at-completion-pmi/)
- [Management reserve](https://pmdecoder.com/en/glossary/management-reserve-pmi/)
- [Contingency reserve](https://pmdecoder.com/en/glossary/contingency-reserve/)
- [Cost management plan](https://pmdecoder.com/en/glossary/cost-management-plan/)
- [Performance measurement baseline](https://pmdecoder.com/en/glossary/performance-measurement-baseline-pmi/)

---