# Project Board

- Framework: [PRINCE2](https://pmdecoder.com/en/framework/prince2/)
- Reference: PRINCE2 7, Praktik Organisation
- Edition: PRINCE2 7
- Concept: [Steering body of a project](https://pmdecoder.com/en/concept/steering-body-of-a-project/)
- Topic area: [Project organization](https://pmdecoder.com/en/area/project-organization/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/project-board/

## Definition

The Project Board is accountable to the commissioning organization for the success of a PRINCE2 project. It brings together three perspectives: the business view through the Executive, the user view through one or more Senior Users and the supplier view through one or more Senior Suppliers. The board authorizes initiation, the project and each stage, sets tolerances, decides on exceptions and confirms closure. It is not a committee of equal votes: the final decision rests with the Executive, who is advised and supported by the other members.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Steering committee](https://pmdecoder.com/en/glossary/steering-committee-pmi/) | closely related | Composed of Executive, Senior User and Senior Supplier; the Executive has the final say. |
| PM² | [Project Steering Committee](https://pmdecoder.com/en/glossary/project-steering-committee/) | closely related | fixed membership chaired by the Project Owner, with the Solution Provider and other roles |
| cross-framework | [Steering committee](https://pmdecoder.com/en/glossary/steering-committee/) | closely related | Composed of Executive, Senior User and Senior Supplier; the Executive has the final say. |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

A steering committee in the general sense is often larger and more broadly composed. The Project Board is deliberately small and built around the three interests. The project steering committee in PM² is similar but distributes roles differently. The Project Board does not run the project day to day; that is the project manager’s task.

## In practice

For the conversion of a hospital to a central emergency department, the Project Board consists of the finance director as Executive, the chief physician of emergency medicine as Senior User and the managing director of the construction contractor as Senior Supplier. It meets at each stage boundary and is convened additionally when fire safety requirements push costs beyond tolerance.

## Frequently asked questions

### How large should a Project Board be?

As small as possible so that it remains able to decide. Several Senior Users or Senior Suppliers are possible if important interests would otherwise be missing.

### Can the Project Board delegate tasks?

Partly. It can, for example, delegate decisions on changes to a Change Authority and assurance to Project Assurance. Accountability for the success of the project remains with the board.

## Related terms

- [Steering committee](https://pmdecoder.com/en/glossary/steering-committee/)
- [Steering committee](https://pmdecoder.com/en/glossary/steering-committee-pmi/)
- [Project Steering Committee](https://pmdecoder.com/en/glossary/project-steering-committee/)
- [Executive (PRINCE2)](https://pmdecoder.com/en/glossary/executive-prince2/)
- [Senior User](https://pmdecoder.com/en/glossary/senior-user/)
- [Senior Supplier](https://pmdecoder.com/en/glossary/senior-supplier/)
- [Directing a project](https://pmdecoder.com/en/glossary/directing-a-project/)
- [Highlight Report](https://pmdecoder.com/en/glossary/highlight-report/)

---