# Progress report

also: Status report

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.60
- Edition: ISO 21506:2024
- Concept: [Regular project status report](https://pmdecoder.com/en/concept/regular-project-status-report/)
- Topic area: [Stakeholders and communication](https://pmdecoder.com/en/area/stakeholders-and-communication/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/progress-report/

## Definition

A progress report summarizes concisely where a project stands. It typically includes an overall assessment, often as a traffic light, the progress made since the last report, the status of schedule, cost and scope, significant risks and issues, and the decisions required from the recipient. It is issued at a fixed interval, usually weekly to monthly.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PRINCE2 | [Highlight Report](https://pmdecoder.com/en/glossary/highlight-report/) | closely related | Report from the Project Manager to the Project Board per management stage, geared to management by exception. |
| PM² | [Project Progress Report](https://pmdecoder.com/en/glossary/project-progress-report/) | closely related | defined PM² artefact from the Project Manager to the Project Steering Committee |
| PRINCE2 | [Checkpoint Report](https://pmdecoder.com/en/glossary/checkpoint-report/) | partially overlapping | Progress report at work package level from the Team Manager to the Project Manager. |

## Distinction

A progress report shows the current position, a final report the overall result at the end. An exception report is prepared as needed when agreed thresholds are exceeded. ISO 21506 uses the term progress report for a report that shows both the current status and the work completed in the reporting period; status report is often used with the same meaning.

## In practice

The project manager of a data centre relocation sends a one-page progress report to the head of IT every Friday. At the top is a traffic light for schedule, cost and quality, below it three sentences on progress and a short list of decisions needed before the following week. When the schedule light turns amber because network equipment is delivered late, the head of IT reacts the same day. A detailed report would probably not have been read that quickly.

## Frequently asked questions

### How reliable are traffic lights in progress reports?

Only as reliable as the organization's culture. If amber and red are punished, reports stay green until it is too late. Criteria defined in advance for each colour help.

### How long should a progress report be?

One page is usually enough for boards and committees. Details belong in appendices that can be read when needed.

## Related terms

- [Project reporting](https://pmdecoder.com/en/glossary/project-reporting/)
- [Control](https://pmdecoder.com/en/glossary/control/)
- [Variance analysis](https://pmdecoder.com/en/glossary/variance-analysis/)
- [Issue](https://pmdecoder.com/en/glossary/issue/)

---