# Programme

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.54
- Edition: ISO 21506:2024
- Concept: [Group of related projects with a shared objective](https://pmdecoder.com/en/concept/group-of-related-projects-with-a-shared-objective/)
- Topic area: [Portfolios and programmes](https://pmdecoder.com/en/area/portfolios-and-programmes/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/programme/

## Definition

A programme brings together projects, subordinate programmes and other work, which ISO 21506 calls programme components. On their own, these do not deliver the desired benefit; only their coordinated interplay does. A programme pursues a strategic objective, such as digitizing a public administration or restructuring a production network, and often runs for several years. New components can be added along the way and others dropped when circumstances change.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Program](https://pmdecoder.com/en/glossary/program/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

A project delivers a defined result, a programme an overarching benefit from several results. A portfolio covers all of an organization's undertakings, even those without any connection in content. Programme management is the steering of a programme, the programme itself is its subject. In everyday language, funding schemes or packages of measures are also called programmes without being managed as programmes in the project management sense.

## In practice

An energy utility launches a programme to switch to renewable heat. It includes projects for three large heat pumps, a heat storage facility, network adaptation, a new tariff model and an information campaign for customers. None of the projects achieves the objective on its own. The programme manager sets the sequence, moves budget between the projects and measures success by the share of renewable heat in the network.

## Frequently asked questions

### When is an undertaking a programme?

When several projects depend on each other, are meant to create a benefit together and therefore have to be steered as a whole.

### Does a programme have a fixed end?

It is usually limited in time, but less sharply than a project. It ends when the intended benefit has been achieved or the organization abandons the objective.

## Related terms

- [Programme component](https://pmdecoder.com/en/glossary/programme-component/)
- [Programme management](https://pmdecoder.com/en/glossary/programme-management/)
- [Programme benefit](https://pmdecoder.com/en/glossary/programme-benefit/)
- [Project](https://pmdecoder.com/en/glossary/project/)
- [Multi-project management](https://pmdecoder.com/en/glossary/multi-project-management/)
- [Portfolio](https://pmdecoder.com/en/glossary/portfolio/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.