# Programme plan

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.59
- Edition: ISO 21506:2024
- Concept: [Plan for managing a programme](https://pmdecoder.com/en/concept/plan-for-managing-a-programme/)
- Topic area: [Portfolios and programmes](https://pmdecoder.com/en/area/portfolios-and-programmes/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/programme-plan/

## Definition

The programme plan describes what a programme is to adhere to. It combines the technical basis, such as architecture, requirements and deliverables, with the baselines for control, such as scope, sequencing of components, budget, resources, risks, benefits and communication. Unlike with a single project, the focus is on how the parts mesh: how are the components connected, and in what order do they lead to the intended benefits?

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Program management plan](https://pmdecoder.com/en/glossary/program-management-plan/) | closely related | emphasizes the approach to programme management, less the planning of content |

## Distinction

The project plan applies to a single project, the programme plan to the programme as a whole and to the interplay of its components; the components' plans have to fit within it. The portfolio plan, by contrast, describes which undertakings support the strategy, not how they are carried out.

## In practice

For a programme to introduce electronic files in a state administration, the programme manager presents a programme plan. It contains the common technical architecture, the order in which twelve ministries will be connected, budget and staffing per year, the benefit targets and the rules for changes. When one ministry wants to start earlier, the programme manager checks against the plan whether the central platform is ready for it.

## Frequently asked questions

### Does the programme plan replace the project plans?

No. Each project component keeps its own project plan. The programme plan sets the framework into which these plans must fit and governs the dependencies between them.

### How often does a programme plan change?

More often than a project plan, because programmes run for a long time and components are added or dropped. Changes are nevertheless decided through a controlled procedure, as with projects.

## Related terms

- [Programme](https://pmdecoder.com/en/glossary/programme/)
- [Project plan](https://pmdecoder.com/en/glossary/project-plan-iso/)
- [Portfolio plan](https://pmdecoder.com/en/glossary/portfolio-plan/)
- [Baseline](https://pmdecoder.com/en/glossary/baseline/)
- [Programme component](https://pmdecoder.com/en/glossary/programme-component/)

---