# Programme management

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.57
- Edition: ISO 21506:2024
- Concept: [Coordinated management of a programme](https://pmdecoder.com/en/concept/coordinated-management-of-a-programme/)
- Topic area: [Portfolios and programmes](https://pmdecoder.com/en/area/portfolios-and-programmes/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/programme-management/

## Definition

Programme management leads a group of projects and accompanying work that depend on each other in content and pursue a common objective. It plans the sequence of the projects, clarifies interfaces, allocates resources between them and makes sure that the intended benefit actually materializes. Programmes often run for several years and bring about fundamental change in organizations.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Program management](https://pmdecoder.com/en/glossary/program-management/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

Project management focuses on a single result, programme management on the overall benefit of several results. Portfolio management covers all projects and programmes of an organization and decides on selection and priority, even if the undertakings have nothing to do with each other. A large project with sub-projects is not yet a programme as long as it delivers a single result.

## In practice

A hospital group brings together the introduction of electronic patient records, the renewal of its networks and the training of all staff in one programme. The programme manager decides that training will only start once the network is in place in the respective hospital, and moves budget when one project finishes under budget. At the end, success is measured not by whether each project was on time, but by whether documentation time per case has fallen.

## Frequently asked questions

### When is a programme worthwhile instead of individual projects?

When several undertakings depend on each other, draw on the same resources and only create their benefit in combination.

### Who leads a programme?

A programme manager who is accountable to management for the overall benefit and coordinates the project managers involved.

## Related terms

- [Project management](https://pmdecoder.com/en/glossary/project-management/)
- [Portfolio management](https://pmdecoder.com/en/glossary/portfolio-management/)
- [Project management office](https://pmdecoder.com/en/glossary/project-management-office/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.