# Programme component

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.56
- Edition: ISO 21506:2024
- Topic area: [Portfolios and programmes](https://pmdecoder.com/en/area/portfolios-and-programmes/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/programme-component/

## Definition

Programme components are the building blocks of a programme. Most are projects that deliver results; others are subordinate programmes for larger sub-areas and other work such as training measures, communication or the transition into operations. No component has to achieve the intended benefit on its own; what matters is its contribution in combination with the others. The programme manager sets the sequence, dependencies and interfaces between the components.

## Equivalents in other frameworks

No equivalents have been recorded for this term yet.

## Distinction

A portfolio component is prioritized against other undertakings, whereas a programme component is coordinated with other components to achieve a common benefit. A sub-project belongs to a single project and delivers part of its result; a programme component is managed in its own right.

## In practice

The programme to introduce a nationwide emergency call system comprises six components: three projects for technology, control centre conversion and interfaces to the rescue services, a subordinate programme for connecting the districts, an ongoing training measure and the transition into regular operations. When the control centre conversion is delayed, the programme manager postpones the start of training so that staff are not trained on technology that is not yet available.

## Frequently asked questions

### Do programme components have to be projects?

No. Work that is not a project in the strict sense, such as ongoing training or organizational measures, can also be a component if it contributes to the benefits.

### Can components change along the way?

Yes. Programmes are designed so that components can be added, adjusted or ended when it becomes clear that the benefits can be achieved better in another way.

## Related terms

- [Programme](https://pmdecoder.com/en/glossary/programme/)
- [Portfolio component](https://pmdecoder.com/en/glossary/portfolio-component/)
- [Programme management](https://pmdecoder.com/en/glossary/programme-management/)
- [Subproject](https://pmdecoder.com/en/glossary/subproject/)

---