# Programme benefit

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.55
- Edition: ISO 21506:2024
- Topic area: [Portfolios and programmes](https://pmdecoder.com/en/area/portfolios-and-programmes/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/programme-benefit/

## Definition

Programme benefits are the real purpose of a programme. They are outcomes, that is, changes that come about when the results are put to use, which can be evaluated and which the programme's stakeholders perceive as positive. Each programme benefit is described with an indicator, a baseline value, a target value and a date, and assigned to a responsible person. The programme plans its components so that these benefits materialize as fully and as promptly as possible.

## Equivalents in other frameworks

No equivalents have been recorded for this term yet.

## Distinction

Benefit is the general term for any positive effect. A programme benefit is narrower: it must be measurable, seen as positive by the stakeholders and contribute to the programme's objectives. A disadvantage experienced by individual stakeholders, such as extra effort in one department, is considered separately.

## In practice

A programme to digitize a city's building control authority sets four programme benefits, including cutting the average permit processing time from four to two months by the end of the third year. The head of the authority is responsible. After the online portal is introduced, the time initially falls only to 3.5 months because documents are still submitted incomplete. The programme adds a component for an automatic completeness check in the portal.

## Frequently asked questions

### How is a programme benefit measured?

With indicators defined in advance, whose baseline values are recorded before the start. Many benefits only materialize gradually, so they are measured several times and often beyond the end of the programme.

### What happens if a programme benefit does not materialize?

The programme manager examines whether components need to be adjusted or added, whether the original assumption was wrong or whether the benefit should be abandoned. The result feeds into further decisions on the programme.

## Related terms

- [Benefit](https://pmdecoder.com/en/glossary/benefit/)
- [Outcome](https://pmdecoder.com/en/glossary/outcome/)
- [Programme](https://pmdecoder.com/en/glossary/programme/)
- [Benefits management](https://pmdecoder.com/en/glossary/benefits-management/)
- [Programme manager](https://pmdecoder.com/en/glossary/programme-manager/)

---