# Program evaluation and review technique

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Schedule estimation with three values per activity](https://pmdecoder.com/en/concept/schedule-estimation-with-three-values-per-activity/)
- Topic area: [Network planning](https://pmdecoder.com/en/area/network-planning/)
- Canonical version: https://pmdecoder.com/en/glossary/program-evaluation-and-review-technique/

## Definition

The program evaluation and review technique, usually called PERT, estimates the duration of an activity not with a single value but with three: an optimistic, a most likely and a pessimistic one. From these a weighted mean is formed, in which the most likely value counts four times and the sum is divided by six. A measure of spread can also be derived from the range between the pessimistic and optimistic values. The technique originated in the late 1950s in a US Navy weapons programme, where it was also used to analyse entire networks.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [PERT](https://pmdecoder.com/en/glossary/pert/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

Program evaluation and review technique is the spelled-out PMI term for the method described in the glossary under PERT. It is a particular form of three-point estimating, which can also use a simple average of the three values. More generally, PMI covers estimating with several values under the term multipoint estimating. The critical path method, by contrast, works with a single duration per activity.

## In practice

For a data centre migration, the team estimates the night in which the servers are moved: six hours at best, eight most likely, sixteen in the worst case. PERT gives nine hours. The project manager therefore plans a ten-hour maintenance window and warns users in advance that it may be extended.

## Frequently asked questions

### Why is the most likely value weighted four times?

The weighting goes back to the assumption of a beta distribution of the duration. It ensures that the most likely value shapes the result while extreme values shift it in their direction.

### Is PERT worthwhile for every activity?

Usually not. It makes sense for activities with high uncertainty or on the critical path. For well-known routine tasks, a single estimate is generally sufficient.

## Related terms

- [PERT](https://pmdecoder.com/en/glossary/pert/)
- [Three-point estimating](https://pmdecoder.com/en/glossary/three-point-estimating/)
- [Multipoint estimating](https://pmdecoder.com/en/glossary/multipoint-estimating/)
- [Critical path method](https://pmdecoder.com/en/glossary/critical-path-method-pmi/)
- [Duration](https://pmdecoder.com/en/glossary/duration/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.