# Product breakdown structure

abbr. PBS

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.53
- Edition: ISO 21506:2024
- Concept: [Hierarchical decomposition of project scope](https://pmdecoder.com/en/concept/decomposing-project-scope/)
- Topic area: [Planning and project structure](https://pmdecoder.com/en/area/planning-and-project-structure/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/product-breakdown-structure/

## Definition

The product breakdown structure divides the overall result of a project into sub-products, such as a building into shell, envelope, building services and external works, or a software system into modules and documents. It describes what should exist at the end, not the activities needed to get there. Deliverables, quality criteria and the work breakdown structure can be derived from it. PRINCE2 explicitly uses this view as the basis for product-based planning.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Work breakdown structure](https://pmdecoder.com/en/glossary/work-breakdown-structure-pmi/) | partially overlapping | breaks down the result into sub-products instead of the work into work packages |
| PRINCE2 | [Product Breakdown Structure](https://pmdecoder.com/en/glossary/product-breakdown-structure-prince2/) | partially overlapping | Breakdown into products rather than work; corresponds to the product breakdown structure under ISO 21506. |
| Scrum | [Product Backlog](https://pmdecoder.com/en/glossary/product-backlog/) | partially overlapping | also decomposes the scope, but ordered by value rather than hierarchically |

## Distinction

The work breakdown structure breaks down the work, the product breakdown structure the result; the two can be closely related. A bill of materials lists the parts of a series product with quantities for manufacturing and purchasing, whereas the product breakdown structure is used to plan a one-off project result and also includes documents and services.

## In practice

For a new employee app, the project team breaks the result down into the app for two operating systems, an administration interface, an interface to the HR software, a data protection concept, training materials and an operations manual. While drawing it up, the team notices that nobody had thought of the operations manual. Only then is the work breakdown structure created, with the work packages that lead to these sub-products.

## Frequently asked questions

### Do you need both a product and a work breakdown structure?

For manageable projects, a results-oriented work breakdown structure is often enough. For complex results, the product breakdown structure helps to ensure that nothing is forgotten.

### What is product-based planning?

A planning approach that first describes the results and then derives the activities and their sequence from them. It prevents work from being planned that does not contribute to any required result.

## Related terms

- [Work breakdown structure](https://pmdecoder.com/en/glossary/work-breakdown-structure/)
- [Bill of materials](https://pmdecoder.com/en/glossary/bill-of-materials/)
- [Deliverable](https://pmdecoder.com/en/glossary/deliverable/)
- [Decomposition](https://pmdecoder.com/en/glossary/decomposition/)

---