# Probability and impact matrix

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Grid of probability and impact](https://pmdecoder.com/en/concept/grid-of-probability-and-impact/)
- Topic area: [Risks and opportunities](https://pmdecoder.com/en/area/risks-and-opportunities/)
- Canonical version: https://pmdecoder.com/en/glossary/probability-and-impact-matrix/

## Definition

In PMI usage, the probability and impact matrix is a grid in which a risk’s probability of occurrence and its impact on project objectives are plotted against each other. Each cell represents a combination of the two and is assigned a priority level, such as high, medium or low. The scales for probability and impact, and the rules for which combination leads to which level, are set by the organization, usually in the risk management plan. PMI provides for threats and opportunities to be shown in the same matrix or in two mirror-image halves. The matrix is a central aid in qualitative risk analysis and makes priorities quickly visible to stakeholders.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Risk matrix](https://pmdecoder.com/en/glossary/risk-matrix/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The probability and impact matrix corresponds to the cross-framework term risk matrix. It is a tool; qualitative risk analysis is the approach in which it is used. Unlike a risk heat map in the broader sense, which may use other axes, it uses exactly these two dimensions.

## In practice

An insurer uses a matrix with five levels on each axis for IT projects. The risk “key person resigns” is rated probability 2 and impact 5 and falls into the red zone, although it is rather unlikely. The project decides to train a deputy. The risk “minor delay in test data” sits in the green zone at 4 and 1 and is only monitored.

## Frequently asked questions

### Why does the organization set the scales rather than the project?

So that risks in different projects are comparable and ratings do not depend on personal standards. The project may adapt the defaults for good reasons but should document this.

### What is the weakness of a probability and impact matrix?

It simplifies a great deal. Coarse levels hide differences within a cell, and ratings often rest on subjective judgments. For important risks, it is therefore supplemented with further criteria or quantitative analyses.

## Related terms

- [Risk matrix](https://pmdecoder.com/en/glossary/risk-matrix/)
- [Qualitative risk analysis](https://pmdecoder.com/en/glossary/qualitative-risk-analysis-pmi/)
- [Risk register](https://pmdecoder.com/en/glossary/risk-register-pmi/)
- [Risk threshold](https://pmdecoder.com/en/glossary/risk-threshold/)
- [Opportunity](https://pmdecoder.com/en/glossary/opportunity-pmi/)
- [Threat](https://pmdecoder.com/en/glossary/threat-pmi/)

---