# Predictive approach

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Plan-driven approach](https://pmdecoder.com/en/concept/plan-driven-approach/)
- Topic area: [Approaches and agility](https://pmdecoder.com/en/area/approaches-and-agility/)
- Canonical version: https://pmdecoder.com/en/glossary/predictive-approach/

## Definition

In PMI’s terms a predictive approach is a development approach that fixes scope, schedule and cost early in the project. It assumes that requirements are largely known and stable and that the way of working can be planned well in advance. The work is organized in phases that usually build on one another and is controlled against an approved baseline. Changes are possible but go through a formal procedure in which their effects are assessed before they are approved. The approach is particularly suitable when late changes become expensive, when regulations require complete documentation or when many parties are bound in by contract.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Traditional project management](https://pmdecoder.com/en/glossary/traditional-project-management/) | closely related | describes the development approach, not project management as a whole |

## Distinction

The cross-framework term traditional project management is closely related but usually denotes the whole of traditional management practice; with the predictive approach PMI mainly describes how results are developed. The waterfall model is a particularly strict form. Its counterpart is the adaptive approach; PMI refers to mixed forms as the hybrid approach.

## In practice

A grid operator builds a substation. Permits, delivery times for transformers and safety regulations are fixed early. The project manager draws up a detailed schedule and budget, which the steering committee approves as the baseline. When a supplier proposes different switchgear, the proposal is assessed through the change procedure.

## Frequently asked questions

### Is a predictive approach outdated?

No. For undertakings with clear requirements and high costs of late change it is often the best choice. PMI treats it on an equal footing with adaptive and hybrid approaches.

### How detailed must planning be at the start?

As detailed as needed for reliable commitments. Even in a predictive approach, work further in the future is often planned roughly at first and refined later.

## Related terms

- [Traditional project management](https://pmdecoder.com/en/glossary/traditional-project-management/)
- [Waterfall model](https://pmdecoder.com/en/glossary/waterfall-model/)
- [Adaptive approach](https://pmdecoder.com/en/glossary/adaptive-approach/)
- [Hybrid approach](https://pmdecoder.com/en/glossary/hybrid-approach/)
- [Project management plan](https://pmdecoder.com/en/glossary/project-management-plan/)
- [Change control](https://pmdecoder.com/en/glossary/change-control-pmi/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.