# Predecessor activity

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Activity on which another depends](https://pmdecoder.com/en/concept/activity-on-which-another-depends/)
- Topic area: [Network planning](https://pmdecoder.com/en/area/network-planning/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/predecessor-activity/

## Definition

A predecessor activity is the activity to whose start or finish another activity is tied in time. An activity can have no, one or several predecessors. If it has several, the one that finishes last determines when it can start at the earliest. Only the start activity of a network schedule has no predecessor.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Predecessor activity](https://pmdecoder.com/en/glossary/predecessor-activity-pmi/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The predecessor is the counterpart of the successor; every logical relationship has exactly one of each. Direct predecessors are linked immediately, indirect ones lie further back in the same chain. An activity that merely comes earlier in the calendar is not a predecessor as long as there is no dependency.

## In practice

In a schedule for a product launch, the activity "Send press release" has three predecessors: approval by the legal department, the finished product photos and confirmation of the sales start by the sales team. Because the photos are delayed by a week, sending is postponed, even though the other two predecessors are finished on time. From the list of predecessors, the press office can see immediately where it needs to follow up.

## Frequently asked questions

### How many predecessors should an activity have?

As many as are actually necessary in substance. Unnecessary links make the plan rigid and distort the critical path.

### What happens if an activity has no predecessor?

In the calculation it starts at the project start. If that is not intended, a link is missing and the network schedule has an open end.

## Related terms

- [Successor activity](https://pmdecoder.com/en/glossary/successor-activity/)
- [Logical relationship](https://pmdecoder.com/en/glossary/logical-relationship/)
- [Activity](https://pmdecoder.com/en/glossary/activity/)

---