# Precedence diagramming method

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Network diagram with activities on nodes](https://pmdecoder.com/en/concept/network-diagram-with-activities-on-nodes/)
- Topic area: [Network planning](https://pmdecoder.com/en/area/network-planning/)
- Canonical version: https://pmdecoder.com/en/glossary/precedence-diagramming-method/

## Definition

The precedence diagramming method, PDM for short, is the technique used to build a schedule model as a network: each activity is represented as a node, usually a box, and the logical relationships between activities are drawn as arrows. PDM allows all four relationship types, finish-to-start, finish-to-finish, start-to-start and start-to-finish, each with a possible lag or lead. The representation is also known as activity-on-node. It underlies almost all current scheduling tools and is the usual input for calculation with the critical path method.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Activity-on-node network](https://pmdecoder.com/en/glossary/activity-on-node-network/) | closely related | names the diagramming method, the activity-on-node network diagram its result |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The precedence diagramming method is close to the German Vorgangsknotennetzplan, but strictly speaking it refers to the technique, while the Vorgangsknotennetzplan is the result. In an activity-on-arrow network (Vorgangspfeilnetzplan), activities lie on the arrows, and dummy activities are often needed to represent dependencies correctly. PMI calls the finished diagram a project schedule network diagram.

## In practice

A municipal utility is planning to replace a water main. The project manager first lays out the activities on cards on a pinboard and links them with arrows, choosing a start-to-start relationship with a lag for trenching and pipe laying, because pipe laying can follow section by section. She then transfers the resulting network into the scheduling tool.

## Frequently asked questions

### Why has the precedence diagramming method prevailed over arrow networks?

It needs no dummy activities, allows all four relationship types and is easier to read and change. In addition, practically all common scheduling tools work on this principle.

### Does the network need to be drawn if a tool does the calculation?

Not necessarily, but a graphical view helps to spot missing or implausible dependencies. Many teams sketch the network together before entering it into the tool.

## Related terms

- [Activity-on-node network](https://pmdecoder.com/en/glossary/activity-on-node-network/)
- [Activity-on-arrow network](https://pmdecoder.com/en/glossary/activity-on-arrow-network/)
- [Project schedule network diagram](https://pmdecoder.com/en/glossary/project-schedule-network-diagram/)
- [Logical relationship](https://pmdecoder.com/en/glossary/logical-relationship-pmi/)
- [Critical path method](https://pmdecoder.com/en/glossary/critical-path-method-pmi/)

---