# Portfolio

also: Project portfolio

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.46
- Edition: ISO 21506:2024
- Concept: [Set of initiatives managed together](https://pmdecoder.com/en/concept/set-of-initiatives-managed-together/)
- Topic area: [Portfolios and programmes](https://pmdecoder.com/en/area/portfolios-and-programmes/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/portfolio/

## Definition

A portfolio brings undertakings together so that an organization can consider, compare and steer them jointly. In ISO 21506 its elements are called portfolio components: projects, programmes, subordinate portfolios and other work. They need not be related in content; they are grouped because they compete for the same resources and are meant to contribute jointly to the strategy. Organizations often maintain an overall portfolio with portfolios for business areas or topics beneath it.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Portfolio](https://pmdecoder.com/en/glossary/portfolio-pmi/) | equivalent | — |

## Distinction

A programme groups related undertakings that create a benefit together; a portfolio can also contain undertakings that are independent of one another. Portfolio management is the activity of steering the portfolio. In German, the term Projektportfolio is also common, even though a portfolio contains more than projects.

## In practice

A machine builder's portfolio comprises 22 development projects, a programme to digitize production and several feasibility studies. Twice a year, a board assesses all components by strategic contribution, risk and resource requirements. When a major customer pulls out, two projects for that customer's industry are stopped and the engineers freed up are assigned to a project intended to open up new markets.

## Frequently asked questions

### How does a portfolio differ from a programme?

A programme groups projects that are related in content and are meant to deliver a benefit together. A portfolio brings projects, programmes and other work together in order to align them with the strategy; they need not be related in content.

### What is portfolio management for?

It decides which initiatives are started, continued, put on hold or stopped, and allocates scarce resources such as budget and specialists. This is meant to ensure that the organization pursues the projects that contribute most to its objectives.

### Can an organization have several portfolios?

Yes. Larger organizations often keep separate portfolios for business units or subject areas, which may in turn feed into a higher-level portfolio.

## Related terms

- [Portfolio component](https://pmdecoder.com/en/glossary/portfolio-component/)
- [Portfolio management](https://pmdecoder.com/en/glossary/portfolio-management/)
- [Portfolio manager](https://pmdecoder.com/en/glossary/portfolio-manager/)
- [Portfolio plan](https://pmdecoder.com/en/glossary/portfolio-plan/)
- [Programme](https://pmdecoder.com/en/glossary/programme/)

---