# Portfolio plan

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.50
- Edition: ISO 21506:2024
- Concept: [Plan for managing a portfolio](https://pmdecoder.com/en/concept/plan-for-managing-a-portfolio/)
- Topic area: [Portfolios and programmes](https://pmdecoder.com/en/area/portfolios-and-programmes/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/portfolio-plan/

## Definition

The portfolio plan makes it clear why a portfolio is composed the way it is. It shows which strategic objectives the portfolio is intended to support and what contribution each component makes. It also contains the agreed baselines for steering the portfolio, such as budget limits, sequencing, capacity, risks and indicators. It is reviewed regularly, usually in step with strategy and budget planning.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Portfolio management plan](https://pmdecoder.com/en/glossary/portfolio-management-plan/) | closely related | describes mainly how the portfolio is managed, less its composition |

## Distinction

The project plan and the programme plan describe how a single undertaking is carried out; the portfolio plan describes which undertakings together support the strategy. A mere list of projects is not yet a portfolio plan, because it lacks the justification and the basis for steering.

## In practice

A municipal utility draws up a five-year portfolio plan for its investment portfolio. It derives three objectives from its climate strategy, assigns 45 undertakings to these objectives and sets annual budget limits and capacity for design and construction. When funding for heating networks increases, the plan shows which undertakings can be brought forward without exceeding capacity limits.

## Frequently asked questions

### How often is a portfolio plan updated?

At least once a year, usually together with budget planning, and additionally when the strategy or key conditions change.

### How does a portfolio plan differ from a strategy?

The strategy sets out what an organization wants to achieve. The portfolio plan translates this into a specific selection of undertakings with resources, timeline and indicators.

## Related terms

- [Portfolio](https://pmdecoder.com/en/glossary/portfolio/)
- [Portfolio management](https://pmdecoder.com/en/glossary/portfolio-management/)
- [Strategic alignment](https://pmdecoder.com/en/glossary/strategic-alignment/)
- [Programme plan](https://pmdecoder.com/en/glossary/programme-plan/)
- [Baseline](https://pmdecoder.com/en/glossary/baseline/)

---