# Portfolio management plan

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Plan for managing a portfolio](https://pmdecoder.com/en/concept/plan-for-managing-a-portfolio/)
- Topic area: [Portfolios and programmes](https://pmdecoder.com/en/area/portfolios-and-programmes/)
- Canonical version: https://pmdecoder.com/en/glossary/portfolio-management-plan/

## Definition

In PMI usage, the portfolio management plan describes how a portfolio is organized, governed and controlled. It defines portfolio governance, that is, bodies, roles and decision paths; the criteria and procedures for selecting, prioritizing and terminating components; the handling of resources and risks at portfolio level; and reporting and communication. It translates strategic direction into a practical way of working and is updated when strategy or circumstances change.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Portfolio plan](https://pmdecoder.com/en/glossary/portfolio-plan/) | closely related | describes mainly how the portfolio is managed, less its composition |

## Distinction

The portfolio plan in the standard concerns the same subject; PMI's portfolio management plan places more emphasis on the procedures for steering than on the list of components, hence the close but not exact match. A roadmap shows the sequence of components over time and key milestones, while the portfolio management plan sets the rules by which the portfolio is managed. The program management plan steers a single program, not the totality of undertakings.

## In practice

A pharmaceutical company prepares a portfolio management plan for its research portfolio. It states that a portfolio board decides twice a year on new drug candidates, which assessment criteria apply, when a project is stopped after negative trial results and how laboratory and trial capacity is allocated. It also specifies which indicators are reported to the executive board.

## Frequently asked questions

### What does a portfolio management plan typically contain?

Governance and roles, selection and prioritization criteria, procedures for adding, reviewing and terminating components, the handling of resources and risks, and reporting lines and communication.

### How often is the portfolio management plan changed?

Less often than the portfolio itself. It is revised when strategy, organization or decision procedures change, not every time an undertaking is added or ended.

## Related terms

- [Portfolio plan](https://pmdecoder.com/en/glossary/portfolio-plan/)
- [Portfolio management](https://pmdecoder.com/en/glossary/portfolio-management-pmi/)
- [Portfolio](https://pmdecoder.com/en/glossary/portfolio-pmi/)
- [Roadmap](https://pmdecoder.com/en/glossary/roadmap-pmi/)
- [Program management plan](https://pmdecoder.com/en/glossary/program-management-plan/)

---