# Plans practice

- Framework: [PRINCE2](https://pmdecoder.com/en/framework/prince2/)
- Reference: PRINCE2 7, Praktik Pläne
- Edition: PRINCE2 7
- Concept: [Working out the path to the project result](https://pmdecoder.com/en/concept/working-out-the-path-to-the-project-result/)
- Topic area: [Planning and project structure](https://pmdecoder.com/en/area/planning-and-project-structure/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/plans-practice/

## Definition

The plans practice sets out how planning is done in a PRINCE2 project and which plans exist. Its hallmark is product-based planning: first the products to be created are described, and only then are activities, dependencies, dates, resources and costs derived from them. The tools for this are the project product description, the product breakdown structure and the product descriptions of individual products. PRINCE2 provides plans at different levels: the project plan for the whole undertaking, stage plans for the management stages and, optionally, team plans. If tolerances are forecast to be exceeded, an exception plan replaces the affected plan.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Project planning](https://pmdecoder.com/en/glossary/project-planning/) | closely related | Product-based planning at several plan levels; planning starts from the results, not the activities. |

## Other terms

- Plans theme (deprecated)

## Distinction

General project planning often starts from activities. The plans practice starts earlier and asks first about the results, in line with the principle of focusing on products. It shares with rolling wave planning the idea of planning only the near stage in detail; it is not a planning process of its own, however, but is applied in several processes.

## In practice

A publisher is preparing a digital learning platform for vocational schools. The project manager first lists the products: course modules, exercise collections, a teacher’s guide, a training concept and the live platform. For each important product a short description with quality criteria is written. Only then are the work steps estimated and transferred into an outline project plan for the whole year and a detailed stage plan for the first three months.

## Frequently asked questions

### Why does PRINCE2 start planning with the products?

Because it is easier to agree on results than on activities. Once the products are described, it is clear what has to be finished, and forgotten work is more likely to be noticed.

### How detailed does a plan need to be?

As detailed as the level concerned needs for its control. The project board needs an overview of the undertaking, the project manager needs detail for the current stage.

## Related terms

- [Project Plan](https://pmdecoder.com/en/glossary/project-plan-prince2/)
- [Stage Plan](https://pmdecoder.com/en/glossary/stage-plan/)
- [Product Breakdown Structure](https://pmdecoder.com/en/glossary/product-breakdown-structure-prince2/)
- [Product Description](https://pmdecoder.com/en/glossary/product-description/)
- [Project planning](https://pmdecoder.com/en/glossary/project-planning/)
- [Rolling wave planning](https://pmdecoder.com/en/glossary/rolling-wave-planning/)
- [Team Plan](https://pmdecoder.com/en/glossary/team-plan/)
- [Exception Plan](https://pmdecoder.com/en/glossary/exception-plan/)

---