# Planned value

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Budgeted value of planned work](https://pmdecoder.com/en/concept/budgeted-value-of-planned-work/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Canonical version: https://pmdecoder.com/en/glossary/planned-value-pmi/

## Definition

In PMI usage, planned value (PV) is the approved budget allocated to the work that the schedule foresees. At any status date, cumulative planned value states how much work, expressed in budget units, should have been completed by then. Summed over the whole duration, it equals the budget at completion. Planned value is derived from the performance measurement baseline and is one of the three basic quantities of earned value analysis, together with earned value and actual cost. It does not include management reserve.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Planned value](https://pmdecoder.com/en/glossary/planned-value/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The term is equivalent to the ISO 21506 term planned value. Planned value says nothing about what has actually been achieved; that is what earned value expresses. Nor should it be confused with planned spending in the sense of a payment plan, because it reflects the value of work rather than the date on which invoices are paid. The earlier term was budgeted cost of work scheduled (BCWS).

## In practice

A project to modernize a production line has a budget of 1.5 million euros and a duration of twelve months. According to the schedule, dismantling, foundation work and delivery of the first machines are to be completed by the end of May; their budgets add up to 520,000 euros. That is the cumulative planned value at this status date. If earned value at the end of May is 460,000 euros, the project is behind schedule.

## Frequently asked questions

### How is the planned value curve created?

The budgets of the work packages or control accounts are spread over time according to the schedule and accumulated. The result is usually an S-shaped curve, because work intensity is highest in the middle of a project.

### Does planned value change during the project?

Only when approved changes are made to the baseline, for example additional scope. Delays alone do not change planned value; otherwise the schedule variance would disappear.

## Related terms

- [Planned value](https://pmdecoder.com/en/glossary/planned-value/)
- [Earned value](https://pmdecoder.com/en/glossary/earned-value/)
- [Actual cost](https://pmdecoder.com/en/glossary/actual-cost-pmi/)
- [Budget at completion](https://pmdecoder.com/en/glossary/budget-at-completion-pmi/)
- [Schedule variance](https://pmdecoder.com/en/glossary/schedule-variance-pmi/)
- [Performance measurement baseline](https://pmdecoder.com/en/glossary/performance-measurement-baseline-pmi/)

---