# Phase Gate

- Framework: [PM²](https://pmdecoder.com/en/framework/pm2/)
- Reference: PM²-Leitfaden 3.1, Abschnitt 3.2.6
- Edition: PM² Guide 3.1
- Concept: [Decision point between project phases](https://pmdecoder.com/en/concept/decision-point-between-project-phases/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Canonical version: https://pmdecoder.com/en/glossary/phase-gate/

## Definition

In PM², a Phase Gate is a checkpoint between two phases of the life cycle. Before the project continues, certain participants, usually the Project Manager, the Project Owner and the Project Steering Committee, check whether the objectives of the completed phase have been achieved. PM² has three such gates: Ready for Planning at the end of initiation, Ready for Executing at the end of planning and Ready for Closing at the end of execution. For each phase there is a phase-exit review checklist that the Project Manager uses to prepare the assessment. The gates support good governance and a controlled course of the project.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Gate](https://pmdecoder.com/en/glossary/gate/) | equivalent | — |
| PMI / PMBOK Guide | [Phase gate](https://pmdecoder.com/en/glossary/phase-gate-pmi/) | equivalent | — |
| Six Sigma | [Tollgate](https://pmdecoder.com/en/glossary/tollgate/) | closely related | between the phases of the DMAIC cycle |
| PRINCE2 | [Managing a stage boundary](https://pmdecoder.com/en/glossary/managing-a-stage-boundary/) | partially overlapping | The Project Manager’s preparation of the decision point; the decision itself is taken by the Project Board. |
| Scrum | — | no counterpart | continuation is decided continuously in the Sprint Review |
| Kanban | — | no counterpart | — |

## Classification

- Narrower terms: [Ready for Closing](https://pmdecoder.com/en/glossary/ready-for-closing/), [Ready for Executing](https://pmdecoder.com/en/glossary/ready-for-executing/), [Ready for Planning](https://pmdecoder.com/en/glossary/ready-for-planning/)

## Distinction

The PM² Phase Gate corresponds to the gate in ISO 21506 and to the phase gate in the PMBOK Guide. A milestone, by contrast, only marks a date and need not be linked to an approval.

## In practice

Before the move into execution, the Project Manager of an archiving project goes through the phase-exit review checklist and finds that the Transition Plan is still missing. He postpones the presentation to the Project Steering Committee by three weeks rather than asking for conditional approval.

## Frequently asked questions

### How many Phase Gates does a PM² project have?

Three: Ready for Planning, Ready for Executing and Ready for Closing. After the Closing Phase, the project ends with the final approval by the Project Owner.

### Are Phase Gates mandatory in PM²?

The guide recommends a review and approval before each transition. How formal it is can be adapted to the size and importance of the project.

## Related terms

- [Ready for Planning](https://pmdecoder.com/en/glossary/ready-for-planning/)
- [Ready for Executing](https://pmdecoder.com/en/glossary/ready-for-executing/)
- [Ready for Closing](https://pmdecoder.com/en/glossary/ready-for-closing/)
- [Project Steering Committee](https://pmdecoder.com/en/glossary/project-steering-committee/)
- [Gate](https://pmdecoder.com/en/glossary/gate/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.