# Phase gate

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Decision point between project phases](https://pmdecoder.com/en/concept/decision-point-between-project-phases/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Canonical version: https://pmdecoder.com/en/glossary/phase-gate-pmi/

## Definition

In PMI usage, a phase gate is a review held when a project or programme phase ends. An authorized body decides whether the undertaking moves on to the next phase, continues with changes or ends. The decision is based on the results of the completed phase, the current status of objectives, cost, schedule and risks, and whether the justification for the undertaking still holds. Phase gates are especially common in predictive life cycles in which phases follow one another. They link project work to the governance of the organization.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Gate](https://pmdecoder.com/en/glossary/gate/) | equivalent | — |
| PM² | [Phase Gate](https://pmdecoder.com/en/glossary/phase-gate/) | equivalent | — |
| Six Sigma | [Tollgate](https://pmdecoder.com/en/glossary/tollgate/) | closely related | between the phases of the DMAIC cycle |
| PRINCE2 | [Managing a stage boundary](https://pmdecoder.com/en/glossary/managing-a-stage-boundary/) | partially overlapping | The Project Manager’s preparation of the decision point; the decision itself is taken by the Project Board. |
| Scrum | — | no counterpart | continuation is decided continuously in the Sprint Review |
| Kanban | — | no counterpart | — |

## Distinction

The ISO 21506 gate and the PM² phase gate are equivalent; the Six Sigma tollgate is closely related but refers to the phases of the improvement cycle. A milestone marks a significant event but does not necessarily require a decision about continuation. A quality review assesses results without deciding on the undertaking as a whole. The phase gate is also known as a phase review, stage gate or kill point.

## In practice

A pharmaceutical company develops a new diagnostic device in four phases. At the end of the concept phase, the project team presents the prototype, the revised cost estimate and the market analysis to the development board. Because the manufacturing cost is well above target, the board releases the next phase only on condition that a cheaper sensor concept is examined. The decision and the condition are recorded in the minutes of the phase gate.

## Frequently asked questions

### Who decides at a phase gate?

A body with decision-making authority over the undertaking, such as the sponsor, a steering committee or a portfolio board. The project manager prepares the documents and makes a recommendation but does not decide.

### Are there phase gates in agile undertakings?

Rarely in pure form, because delivery and adjustment happen continuously. In hybrid approaches, however, gates remain common, for example before series production or before a major investment decision.

## Related terms

- [Gate](https://pmdecoder.com/en/glossary/gate/)
- [Phase Gate](https://pmdecoder.com/en/glossary/phase-gate/)
- [Tollgate](https://pmdecoder.com/en/glossary/tollgate/)
- [Project phase](https://pmdecoder.com/en/glossary/project-phase-pmi/)
- [Project life cycle](https://pmdecoder.com/en/glossary/project-life-cycle-pmi/)
- [Business case](https://pmdecoder.com/en/glossary/business-case-pmi/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.