# PERT

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Schedule estimation with three values per activity](https://pmdecoder.com/en/concept/schedule-estimation-with-three-values-per-activity/)
- Topic area: [Network planning](https://pmdecoder.com/en/area/network-planning/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/pert/

## Definition

PERT, the Program Evaluation and Review Technique, was developed in the United States in the late 1950s for a large defence programme involving many novel tasks. Each duration is estimated with an optimistic, a most likely and a pessimistic value. These yield a weighted expected value and a variance. By summing the expected values and the variances along the critical path, it is possible to estimate the probability of meeting an end date. Classically, PERT works with event-oriented network schedules.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Program evaluation and review technique](https://pmdecoder.com/en/glossary/program-evaluation-and-review-technique/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The critical path method works with fixed durations, PERT with ranges. The estimates come from three-point estimating, on which PERT builds a complete planning method. A Monte Carlo simulation considers all paths at the same time and thus avoids a known weakness of PERT: underestimating the effect of several near-critical paths converging.

## In practice

A research institute plans to build a prototype with twelve activities, some of which are being carried out for the first time. For each activity, the experts provide three estimates. The calculation gives an expected value of 38 weeks for the critical path with a standard deviation of three weeks. The funding body asks for a reliable date; the institute states 44 weeks, which according to this calculation will be met with high probability.

## Frequently asked questions

### How does PERT calculate the expected value?

As the optimistic value plus four times the most likely value plus the pessimistic value, divided by six. The standard deviation is approximated as the difference between the pessimistic and optimistic values, divided by six.

### Is PERT still used today?

The full method rarely, but its estimating approach frequently, often in combination with simulations.

## Related terms

- [Three-point estimating](https://pmdecoder.com/en/glossary/three-point-estimating/)
- [Network planning technique](https://pmdecoder.com/en/glossary/network-planning-technique/)
- [Critical path method](https://pmdecoder.com/en/glossary/critical-path-method/)
- [Monte Carlo simulation](https://pmdecoder.com/en/glossary/monte-carlo-simulation/)

---