# Performance measurement baseline

abbr. PMB

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.44
- Edition: ISO 21506:2024
- Concept: [Time-phased baseline for performance measurement](https://pmdecoder.com/en/concept/time-phased-baseline-for-performance-measurement/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/performance-measurement-baseline/

## Definition

The performance measurement baseline brings together which work is to be done when and what budget is intended for it. It consists of the time-phased budgets of all control accounts plus the budget not yet distributed. It yields the planned value for every cut-off date, and at the end it equals the budget at completion of the project. The management reserve is explicitly excluded, so that the measurement is not distorted by funds that have not yet been assigned to any work.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Performance measurement baseline](https://pmdecoder.com/en/glossary/performance-measurement-baseline-pmi/) | equivalent | — |

## Distinction

Baseline is the general term for an approved reference version, often kept separately for scope, schedule and cost. The performance measurement baseline is the integrated form in which these three are inseparably linked. The overall project budget is larger because it also contains the management reserve.

## In practice

A satellite project has a total budget of 85 million euros. Of this, 80 million are spread across 31 control accounts and 36 months in the performance measurement baseline, while 5 million remain with programme management as management reserve. The baseline curve shows a planned value of 26 million euros for month twelve. Every approved change, including every release from the reserve, is incorporated into the baseline in a traceable way.

## Frequently asked questions

### May the performance measurement baseline be changed?

Yes, but only through a defined change procedure, for example after approved scope changes or releases from the management reserve. Retroactive adjustments that make variances disappear are not permitted.

### Why is the German glossary using an English term here?

No single German translation has become established in earned value management practice. The abbreviation PMB is common in reports and tools.

## Related terms

- [Baseline](https://pmdecoder.com/en/glossary/baseline/)
- [Planned value](https://pmdecoder.com/en/glossary/planned-value/)
- [Management reserve](https://pmdecoder.com/en/glossary/management-reserve/)
- [Control account](https://pmdecoder.com/en/glossary/control-account/)
- [Time-phased budget](https://pmdecoder.com/en/glossary/time-phased-budget/)
- [Undistributed budget](https://pmdecoder.com/en/glossary/undistributed-budget/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.