# Performance measurement baseline

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Time-phased baseline for performance measurement](https://pmdecoder.com/en/concept/time-phased-baseline-for-performance-measurement/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Canonical version: https://pmdecoder.com/en/glossary/performance-measurement-baseline-pmi/

## Definition

In PMI usage, the performance measurement baseline (PMB) combines the scope, schedule and cost baselines into a single approved yardstick. It shows which work is to be done when and with what budget, and is therefore time-phased. Planned value, earned value and actual cost are compared against it. Management reserve is not part of the PMB, whereas contingency reserves for known risks are included in the cost baseline. The PMB is changed only through formal change control, so that variances do not disappear through quiet replanning.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Performance measurement baseline](https://pmdecoder.com/en/glossary/performance-measurement-baseline/) | equivalent | — |

## Distinction

The PMI term is equivalent to the ISO 21506 term of the same name. A single baseline covers only one subject, such as the schedule; the PMB integrates all three. The project budget is larger than the PMB because it also includes the management reserve. The total of the PMB at project end equals the budget at completion.

## In practice

For a defence programme, the customer requires earned value management. The project derives twelve control accounts from the work breakdown structure, spreads their budgets across the months of the project and sets the cumulative curve as the PMB. When a design change is approved, the project adjusts the affected control accounts through a documented change request. All others remain unchanged, so the variance reports stay comparable.

## Frequently asked questions

### Why is management reserve not part of the PMB?

Because it is intended for unforeseen work within scope that cannot yet be assigned to a work package or time period. Only when it is released and allocated to work does the amount move into the PMB.

### How often may the PMB be changed?

As rarely as possible, and only for approved changes to scope, schedule or budget. Frequent replanning hides variances and undermines performance measurement.

## Related terms

- [Performance measurement baseline](https://pmdecoder.com/en/glossary/performance-measurement-baseline/)
- [Baseline](https://pmdecoder.com/en/glossary/baseline-pmi/)
- [Earned value management](https://pmdecoder.com/en/glossary/earned-value-management-pmi/)
- [Control account](https://pmdecoder.com/en/glossary/control-account-pmi/)
- [Management reserve](https://pmdecoder.com/en/glossary/management-reserve-pmi/)
- [Planned value](https://pmdecoder.com/en/glossary/planned-value-pmi/)

---