# Percent complete

also: Degree of completion, Percentage of completion

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Share of work completed](https://pmdecoder.com/en/concept/share-of-work-completed/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/percent-complete/

## Definition

Percent complete expresses how far a piece of work has progressed. Because progress is often hard to measure, there are various methods: the ratio of completed to planned quantities, fixed steps such as 0, 50 and 100 per cent, weighted interim results within a work package, or the judgement of the person responsible. It is a central quantity in progress measurement and in earned value analysis.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Percent complete](https://pmdecoder.com/en/glossary/percent-complete-pmi/) | equivalent | — |

## Distinction

Percent complete measures the work performed, not the effort consumed: someone who has spent half the budget is not necessarily half finished. Elapsed time is not a measure of progress either. The German term Fortschrittsgrad is used partly as a synonym and partly for the project as a whole.

## In practice

In a road construction project, a contractor has been reporting ninety per cent completion of the asphalt work for weeks. Project control switches to a quantity-based method: what counts as finished is what has been laid and inspected in square metres. The value drops to 72 per cent, but it is reliable. For design work without measurable quantities, by contrast, the rule is that a work package counts as half finished when the draft is submitted and as finished when it is approved.

## Frequently asked questions

### Why does work often stay at ninety per cent for a long time?

Because progress is estimated by feel and the last steps, such as tests, coordination and corrections, are underestimated.

### Which measurement method is best?

That depends on the work. Quantity-based methods are the most objective; fixed steps are simple and prevent inflated interim values.

## Related terms

- [Control](https://pmdecoder.com/en/glossary/control/)
- [Earned value management](https://pmdecoder.com/en/glossary/earned-value-management/)
- [Earned value](https://pmdecoder.com/en/glossary/earned-value/)
- [Work package](https://pmdecoder.com/en/glossary/work-package/)
- [Variance analysis](https://pmdecoder.com/en/glossary/variance-analysis/)

---