# Percent complete

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Share of work completed](https://pmdecoder.com/en/concept/share-of-work-completed/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Canonical version: https://pmdecoder.com/en/glossary/percent-complete-pmi/

## Definition

In PMI usage, percent complete estimates, as a percentage, how much of the work of an activity or of an element of the work breakdown structure has been completed. It is a key input to earned value analysis, because together with the budget it determines the earned value. Its reliability depends on the measurement method: fixed rules such as 0/100 or 50/50, weighted intermediate results or counted units are more objective than a free estimate by those involved.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Percent complete](https://pmdecoder.com/en/glossary/percent-complete/) | equivalent | — |

## Distinction

The term corresponds to the cross-framework term degree of completion. It should not be confused with the share of elapsed duration or of cost spent: an activity may have used half its time and budget and still be only one third complete. Scheduling tools sometimes have separate fields for duration and work progress, which are not the same as physical progress.

## In practice

In a project to renew a water main, 1.2 of 3 kilometres have been laid. Rather than asking the site manager for an estimate, project controls use the metres measured and report 40 percent for the work package. For the “Permits” work package, the 0/100 rule applies because a permit has either been granted or not. This keeps the reported progress traceable.

## Frequently asked questions

### Why do activities often stay at 90 percent for a long time?

Because freely estimated values underestimate the effort for completion, testing and rework. Objective measurement rules or smaller work packages prevent this so-called 90 percent syndrome.

### Which measurement method suits short activities?

For activities completed within one or two reporting periods, fixed rules such as 0/100 or 50/50 are sufficient. They are easy to apply and leave little room for embellishment.

## Related terms

- [Percent complete](https://pmdecoder.com/en/glossary/percent-complete/)
- [Earned value](https://pmdecoder.com/en/glossary/earned-value/)
- [Work package](https://pmdecoder.com/en/glossary/work-package-pmi/)
- [Activity](https://pmdecoder.com/en/glossary/activity-pmi/)
- [Planned value](https://pmdecoder.com/en/glossary/planned-value-pmi/)

---