# Parametric estimating

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Estimating using statistical parameters](https://pmdecoder.com/en/concept/estimating-using-statistical-parameters/)
- Topic area: [Resources and estimating](https://pmdecoder.com/en/area/resources-and-estimating/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/parametric-estimating/

## Definition

Parametric estimating uses experience in the form of calculation rules, such as cost per square metre of office space, hours per kilometre of cable or effort per function point of software. The quantity of the new undertaking is multiplied by the rate or entered into a more extensive model. Accuracy depends on how well the relationship is supported by evidence and whether the new project falls within the range of the underlying data.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Parametric estimating](https://pmdecoder.com/en/glossary/parametric-estimating-pmi/) | equivalent | — |

## Classification

- Broader term: [Effort estimation](https://pmdecoder.com/en/glossary/effort-estimation/)

## Distinction

Analogous estimating transfers the values of a similar project as a whole; parametric estimating calculates with rates per unit. Bottom-up estimating estimates individual work packages and adds them up. Parametric models such as cost benchmarks in construction or function point methods in software development are often in use across entire industries.

## In practice

A fibre-optic company connects municipalities in rural areas. From forty completed roll-out areas, it knows average values for civil works per metre of route, for building connections and for planning effort per connection. For a new area with 1,200 connections and 38 kilometres of route, the planners scale up these rates. Because the ground there is rocky, the civil works rate receives a surcharge taken from two similar areas.

## Frequently asked questions

### Where do the rates come from?

From the organization's own historical data, from industry associations, from databases or from published studies. The organization's own values usually fit best.

### When does parametric estimating fail?

When the new undertaking differs fundamentally from the projects behind the data, for example in size, technology or site conditions.

## Related terms

- [Analogous estimating](https://pmdecoder.com/en/glossary/analogous-estimating/)
- [Historical data](https://pmdecoder.com/en/glossary/historical-data/)
- [Cost estimation](https://pmdecoder.com/en/glossary/cost-estimation/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.