# Organizing practice

- Framework: [PRINCE2](https://pmdecoder.com/en/framework/prince2/)
- Reference: PRINCE2 7, Praktik Organisation
- Edition: PRINCE2 7
- Concept: [Roles, bodies and authority in a project](https://pmdecoder.com/en/concept/roles-bodies-and-authority-in-a-project/)
- Topic area: [Project organization](https://pmdecoder.com/en/area/project-organization/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/organizing-practice/

## Definition

The organizing practice sets out who is responsible for what in a project and how the people involved work together. PRINCE2 distinguishes several levels: the commissioning organization outside the project, the project board that directs the project, the project manager who manages it day to day, and the teams that deliver the products. The project board is expected to represent three interests: the business view, the view of the future users and the view of the suppliers. The practice puts into effect the principle of clearly defined roles, responsibilities and relationships. PRINCE2 7 places more weight than earlier editions on relationships with stakeholders and on working with suppliers.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Project organization](https://pmdecoder.com/en/glossary/project-organization/) | closely related | Fixed role model with project board, project manager and team managers, tailored to the project. |

## Other terms

- Organization theme (deprecated)

## Distinction

A general project organization describes any structure of roles and bodies. The organizing practice provides a fixed role model for it, which is tailored to project size and context, for example by one person taking on several roles. Unlike a job description, PRINCE2 assigns roles rather than positions; a role can be shared or combined with another.

## In practice

A mechanical engineering company is introducing new planning software. The head of production takes the executive role, two shift supervisors represent the future users as senior users, and the sales manager of the software vendor sits on the project board as senior supplier. The project manager comes from internal IT. Because the project is small, the project manager also provides project support. This tailoring is recorded in the project documentation.

## Frequently asked questions

### Why is the supplier represented on the project board?

Because the board’s decisions depend on whether the planned products can be delivered technically and with the available resources. The supplier side contributes this assessment.

### Does every role need a separate person?

No. Roles can be combined or split. What must be avoided is losing important checks, for example when the project manager also judges their own work.

## Related terms

- [Project organization](https://pmdecoder.com/en/glossary/project-organization/)
- [Steering committee](https://pmdecoder.com/en/glossary/steering-committee/)
- [Project manager](https://pmdecoder.com/en/glossary/project-manager/)
- [Communication Management Approach](https://pmdecoder.com/en/glossary/communication-management-approach/)
- [Commercial Management Approach](https://pmdecoder.com/en/glossary/commercial-management-approach/)
- [Define roles, responsibilities and relationships](https://pmdecoder.com/en/glossary/define-roles-responsibilities-and-relationships/)
- [Project Board](https://pmdecoder.com/en/glossary/project-board/)
- [Project Manager (PRINCE2)](https://pmdecoder.com/en/glossary/project-manager-prince2/)

---