# Organizational breakdown structure

abbr. OBS

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.40
- Edition: ISO 21506:2024
- Concept: [Hierarchical breakdown of the project organization](https://pmdecoder.com/en/concept/hierarchical-breakdown-of-the-project-organization/)
- Topic area: [Project organization](https://pmdecoder.com/en/area/project-organization/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/organizational-breakdown-structure/

## Definition

The organizational breakdown structure shows which units are involved in an undertaking and how they are structured: departments, teams, partner companies and subcontractors, down to the positions that own the work. Placed next to the work breakdown structure, it shows which unit manages or performs which work. The points where the two structures intersect are where control accounts are usually formed. It can also cover the leadership team of a whole organization.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Organizational breakdown structure](https://pmdecoder.com/en/glossary/organizational-breakdown-structure-pmi/) | equivalent | — |

## Distinction

A company's organization chart depicts the permanent line organization, while the organizational breakdown structure depicts the organization of a specific undertaking, including across company boundaries. The responsibility assignment matrix assigns individual tasks and types of involvement, whereas the organizational breakdown structure shows the structure of the units themselves.

## In practice

For the construction of an offshore wind farm, the operator draws up an organizational breakdown structure with four main areas: its own project company, the foundation manufacturer, the turbine supplier and the grid operator, each with its sub-project teams. Comparing it with the work breakdown structure reveals that the work package "Cable pull-in into the turbines" has not been assigned to any unit, because the turbine supplier and the cable installer each thought the other was responsible. Responsibility is clarified in the contracts.

## Frequently asked questions

### Who belongs in the organizational breakdown structure?

All units that manage or perform work in the undertaking, including external partners and major subcontractors. Individual people are usually named only at the lowest level.

### Why is it needed in earned value management?

To assign a responsible unit to every piece of work. Crossing the work breakdown structure with the organizational breakdown structure yields the control accounts that are measured and reported on.

## Related terms

- [Work breakdown structure](https://pmdecoder.com/en/glossary/work-breakdown-structure/)
- [Control account](https://pmdecoder.com/en/glossary/control-account/)
- [Responsibility assignment matrix](https://pmdecoder.com/en/glossary/responsibility-assignment-matrix/)
- [Organization chart](https://pmdecoder.com/en/glossary/organization-chart/)
- [Project organization](https://pmdecoder.com/en/glossary/project-organization/)

---