# Organizational breakdown structure

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Hierarchical breakdown of the project organization](https://pmdecoder.com/en/concept/hierarchical-breakdown-of-the-project-organization/)
- Topic area: [Project organization](https://pmdecoder.com/en/area/project-organization/)
- Canonical version: https://pmdecoder.com/en/glossary/organizational-breakdown-structure-pmi/

## Definition

In PMI usage, the organizational breakdown structure (OBS) is a hierarchical breakdown of the organization involved in a project. It arranges departments, teams, partners or suppliers in levels and links them to the work they take on. In this way it answers the question of which unit is responsible for which work packages or activities. Combined with the work breakdown structure, it produces a view of the project in which scope and performing units are related to each other; the control accounts of earned value management often sit at the points where the two intersect.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Organizational breakdown structure](https://pmdecoder.com/en/glossary/organizational-breakdown-structure/) | equivalent | — |

## Distinction

The concept corresponds to the organizational breakdown structure as described in the standard; PMI uses the OBS mainly to assign work and responsibility. Unlike the work breakdown structure, the OBS does not break down the scope but the parties involved. The resource breakdown structure groups resources by category and type, while the project organization chart shows people and their relationships within the project team without necessarily linking them to work packages.

## In practice

A plant engineering company is building a bottling line. The OBS is divided into design, manufacturing, installation and commissioning, plus two external suppliers for the control system and the conveyor. Each unit is assigned to the work packages of the work breakdown structure that it performs. The comparison shows that the interface tests are assigned neither to installation nor to the control system supplier; the project manager clarifies responsibility before work starts.

## Frequently asked questions

### Why is an OBS needed in addition to the work breakdown structure?

The work breakdown structure shows what has to be done, the OBS who does it. Only by linking the two do gaps and duplicate responsibilities become visible, and together they form the basis for responsibility assignment matrices and control accounts.

### Does the OBS have to match the line organization?

No. It reflects the organization as it actually contributes to the project and may include external partners, working groups or temporary teams that do not appear on the company's organization chart.

## Related terms

- [Organizational breakdown structure](https://pmdecoder.com/en/glossary/organizational-breakdown-structure/)
- [Work breakdown structure](https://pmdecoder.com/en/glossary/work-breakdown-structure-pmi/)
- [Responsibility assignment matrix](https://pmdecoder.com/en/glossary/responsibility-assignment-matrix-pmi/)
- [Resource breakdown structure](https://pmdecoder.com/en/glossary/resource-breakdown-structure-pmi/)
- [Project organization chart](https://pmdecoder.com/en/glossary/project-organization-chart/)

---