# Opportunity

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.39
- Edition: ISO 21506:2024
- Concept: [Risk with a positive effect on project objectives](https://pmdecoder.com/en/concept/risk-with-a-positive-effect-on-project-objectives/)
- Topic area: [Risks and opportunities](https://pmdecoder.com/en/area/risks-and-opportunities/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/opportunity/

## Definition

An opportunity is the positive side of uncertainty. It exists when something could happen that would allow a project to finish faster, more cheaply, better or with greater benefit, such as falling material prices, an early permit or a new technique that saves work. Opportunities are identified, assessed and given responses in the same way as threats, so that they are actually exploited.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Opportunity](https://pmdecoder.com/en/glossary/opportunity-pmi/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

ISO 21506 treats opportunities and threats alike as risks, whereas in everyday language risk usually means only the negative side. The threat is the counterpart of the opportunity. In a SWOT analysis, opportunities are external possibilities, while strengths are internal characteristics.

## In practice

While planning a new administrative building, the project team learns that a funding programme for timber construction is about to be launched. The opportunity is entered in the register: medium probability, potential grant of up to ten per cent. As a response, the team has a timber structural design checked in parallel so that an application can be submitted immediately. When the programme starts, the client submits the application in the first week.

## Frequently asked questions

### How are opportunities handled?

With strategies that mirror those for threats: making them happen deliberately, enhancing them, sharing them with partners or consciously waiting.

### Why are opportunities often overlooked?

Because risk workshops usually ask about dangers. A separate question about possible improvements helps to capture opportunities systematically.

## Related terms

- [Threat](https://pmdecoder.com/en/glossary/threat/)
- [Risk](https://pmdecoder.com/en/glossary/risk/)
- [SWOT analysis](https://pmdecoder.com/en/glossary/swot-analysis/)
- [Risk response](https://pmdecoder.com/en/glossary/risk-response/)

---