# Opportunity

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Risk with a positive effect on project objectives](https://pmdecoder.com/en/concept/risk-with-a-positive-effect-on-project-objectives/)
- Topic area: [Risks and opportunities](https://pmdecoder.com/en/area/risks-and-opportunities/)
- Canonical version: https://pmdecoder.com/en/glossary/opportunity-pmi/

## Definition

PMI understands risk as an uncertain event or circumstance whose occurrence would affect objectives favourably or unfavourably. An opportunity is the positive side of this understanding: a risk that would benefit the project, for example through lower costs, faster completion or greater benefit. Opportunities are identified, assessed and recorded in the risk register in the same way as threats. They have their own response strategies: exploit seeks to ensure that the opportunity occurs, enhance increases its probability or impact, share involves a partner better able to capture it, and accept takes it without active intervention. If the opportunity lies outside the project’s authority, escalate is an option.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Opportunity](https://pmdecoder.com/en/glossary/opportunity/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Classification

- Broader term: [Risk](https://pmdecoder.com/en/glossary/risk-pmi/)

## Distinction

The opportunity corresponds to the Chance of ISO 21506. Its counterpart is the threat, the risk with a negative effect. It does not refer to a business opportunity in the sales sense, such as a potential order, which is also called an opportunity in sales planning.

## In practice

While planning a production line, the team learns that a supplier intends to launch a new controller with lower energy consumption next quarter. If this happens, operating costs will fall considerably. The team records the opportunity in the risk register and chooses the enhance strategy: it arranges to take part in the supplier’s pilot programme and keeps the controller order open until the cut-off date.

## Frequently asked questions

### Why does PMI treat opportunities as risks?

Because both arise from uncertainty and can be identified and assessed with the same means. Looking only at threats misses ways to achieve objectives better and tends to lead to overly pessimistic plans.

### How does exploit differ from enhance?

Exploit tries to remove the uncertainty entirely so that the opportunity definitely occurs. Enhance only improves the prospects by increasing probability or impact, without guaranteeing that it occurs.

## Related terms

- [Opportunity](https://pmdecoder.com/en/glossary/opportunity/)
- [Risk](https://pmdecoder.com/en/glossary/risk-pmi/)
- [Threat](https://pmdecoder.com/en/glossary/threat-pmi/)
- [Risk response](https://pmdecoder.com/en/glossary/risk-response-pmi/)
- [Expected monetary value](https://pmdecoder.com/en/glossary/expected-monetary-value-pmi/)

---