# Network schedule

also: Network diagram

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.38
- Edition: ISO 21506:2024
- Concept: [Diagram of activities and their dependencies](https://pmdecoder.com/en/concept/diagram-of-activities-and-their-dependencies/)
- Topic area: [Network planning](https://pmdecoder.com/en/area/network-planning/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/network-schedule/

## Definition

A network schedule shows which activities or events a project comprises and how they are logically linked. Each path from start to finish represents a chain of work in which each step builds on the one before. Together with the durations, the network schedule allows the earliest and latest dates, the float and the critical path to be calculated. A correct network schedule has exactly one start point and one end point, no loops and no open ends.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Project schedule network diagram](https://pmdecoder.com/en/glossary/project-schedule-network-diagram/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The network schedule is the result of network planning techniques. A distinction is made between activity-on-node, activity-on-arrow and event-on-node diagrams. A time-scaled network schedule additionally arranges the nodes along a time axis and thus comes close to a linked bar chart.

## In practice

When checking the network schedule for a tunnelling project, the planning software reports two errors: one activity has no successor, and three others form a loop. The open activity is the documentation of the drilling results, which had simply not been linked to the planning approval. The loop arises because planning and review each have the other as predecessor. The team resolves it by entering the revision as a separate activity.

## Frequently asked questions

### Why are loops not allowed in a network schedule?

Because dates can then no longer be calculated: every activity in the loop would have to finish before itself. Repetitions are shown as separate activities.

### What is an open end?

An activity with no predecessor or no successor that is not the start or end of the project. It usually results from forgotten links and distorts the float calculation.

## Related terms

- [Network planning technique](https://pmdecoder.com/en/glossary/network-planning-technique/)
- [Activity-on-node network](https://pmdecoder.com/en/glossary/activity-on-node-network/)
- [Activity-on-arrow network](https://pmdecoder.com/en/glossary/activity-on-arrow-network/)
- [Subnetwork](https://pmdecoder.com/en/glossary/subnetwork/)
- [Critical path](https://pmdecoder.com/en/glossary/critical-path/)
- [Activity sequence plan](https://pmdecoder.com/en/glossary/activity-sequence-plan/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.