# Multipoint estimating

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Estimating with several values per quantity](https://pmdecoder.com/en/concept/estimating-with-several-values-per-quantity/)
- Topic area: [Resources and estimating](https://pmdecoder.com/en/area/resources-and-estimating/)
- Canonical version: https://pmdecoder.com/en/glossary/multipoint-estimating/

## Definition

In PMI usage, multipoint estimating covers estimating techniques that collect several values rather than one for a quantity, in order to make uncertainty visible. The most common form uses three values: an optimistic, a most likely and a pessimistic one. An expected value is calculated from them, either as the simple average of the three, which corresponds to a triangular distribution, or as a weighted average in which the most likely value counts four times and the sum is divided by six, which corresponds to the beta distribution of the PERT method. Besides the expected value, the spread can be estimated, giving a range within which the result lies with a certain probability.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Three-point estimating](https://pmdecoder.com/en/glossary/three-point-estimating/) | equivalent | — |

## Distinction

In the concept, the three-point estimate is the preferred term. Multipoint estimating is somewhat broader, because the name also includes techniques with more than three reference values; in practice the three-point form is usually meant. The program evaluation and review technique is a specific application of this estimate to activity durations in a network.

## In practice

For the approval of a building application, the specialist planner gives three values: six weeks at best, probably ten weeks, and in the worst case 20 weeks if further documents are requested. The weighted formula yields an expected value of eleven weeks. The project manager plans with eleven weeks but decides that structural steel will be ordered only after approval, because the upper range is wide.

## Frequently asked questions

### When is the simple average used, and when the weighted one?

The weighted average suits cases in which the most likely value is well founded and the extremes occur less often. The simple average gives the extremes more weight and is more cautious when little experience is available.

### Where do the three values come from?

From expert interviews, historical data or both. It is important that the extreme values are realistic and do not deviate only slightly from the most likely value; otherwise the calculation underestimates the uncertainty.

## Related terms

- [Three-point estimating](https://pmdecoder.com/en/glossary/three-point-estimating/)
- [PERT](https://pmdecoder.com/en/glossary/pert/)
- [Program evaluation and review technique](https://pmdecoder.com/en/glossary/program-evaluation-and-review-technique/)
- [Quantitative risk analysis](https://pmdecoder.com/en/glossary/quantitative-risk-analysis-pmi/)
- [Parametric estimating](https://pmdecoder.com/en/glossary/parametric-estimating-pmi/)

---