# Monte Carlo simulation

also: Monte Carlo analysis, Monte Carlo method

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Topic area: [Risks and opportunities](https://pmdecoder.com/en/area/risks-and-opportunities/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/monte-carlo-simulation/

## Definition

In a Monte Carlo simulation, uncertain variables such as activity durations or cost items are entered not as fixed numbers but as distributions, for example based on three-point estimates. The computer randomly draws a value for each variable, calculates the result and repeats this run many thousands of times. All the results together form a distribution that shows the probability of meeting a particular date or budget.

## Equivalents in other frameworks

No equivalents have been recorded for this term yet.

## Distinction

The critical path method calculates with fixed durations and produces exactly one end date; the simulation produces a range with probabilities. Sensitivity analysis shows which input variables influence the result most and is often evaluated together with the simulation. The name alludes to the casino in Monte Carlo, because the method works with random numbers.

## In practice

A construction company is to commit contractually to a completion date for a multi-storey car park. The simulation, with ranges for 45 activities, shows that the planned date will be met with a probability of only 30 per cent, and a date six weeks later with 80 per cent. The company offers the later date and uses the distribution to show the client why an earlier date would very probably trigger contractual penalties.

## Frequently asked questions

### How many runs does a simulation need?

A few thousand is usual. Beyond that number, the results generally hardly change.

### Is the simulation more accurate than normal planning?

It is more honest, because it makes uncertainty visible. Its accuracy, however, depends entirely on the ranges and dependencies entered.

## Related terms

- [Quantitative risk analysis](https://pmdecoder.com/en/glossary/quantitative-risk-analysis/)
- [Three-point estimating](https://pmdecoder.com/en/glossary/three-point-estimating/)
- [Sensitivity analysis](https://pmdecoder.com/en/glossary/sensitivity-analysis/)
- [Critical path method](https://pmdecoder.com/en/glossary/critical-path-method/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.