# Monitor & Control

- Framework: [PM²](https://pmdecoder.com/en/framework/pm2/)
- Reference: PM²-Leitfaden 3.1, Abschnitte 3.2.5 und 9
- Edition: PM² Guide 3.1
- Concept: [Monitoring and controlling a project](https://pmdecoder.com/en/concept/monitoring-and-controlling-a-project/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Canonical version: https://pmdecoder.com/en/glossary/monitor-and-control/

## Definition

In PM², Monitor & Control covers all activities used to observe, measure and steer the project work throughout the entire life cycle. The Project Manager compares progress with the plans, detects deviations, decides on corrective actions and deals with risks and issues. The guide divides this area into processes for project performance, schedule, costs, stakeholders, requirements, changes, risks, issues and decisions, quality, deliverables acceptance, transition, business implementation and outsourcing.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Control](https://pmdecoder.com/en/glossary/control/) | closely related | described in PM² as a separate group of activities spanning all phases |
| PRINCE2 | [Progress practice](https://pmdecoder.com/en/glossary/progress-practice/) | closely related | Control through tolerances and management by exception with fixed escalation levels. |
| PRINCE2 | [Controlling a stage](https://pmdecoder.com/en/glossary/controlling-a-stage/) | partially overlapping | Control of a single stage by the Project Manager; Project Board decisions belong to other processes. |

## Distinction

In the PM² life cycle, Monitor & Control is not a fifth phase in the sequence but runs in parallel with all four phases. The general term project control refers to the same field of tasks; PM² additionally assigns fixed processes, logs and reports to it.

## In practice

In an office relocation project, the Project Manager checks dates and costs against the baseline every week, keeps the risk log up to date and decides on minor replanning herself. When the furniture supplier reports a two-week delay, she submits a change request with two alternative dates to the Project Steering Committee.

## Frequently asked questions

### Is Monitor & Control a separate phase?

No. Although the guide occasionally speaks of a phase, it presents Monitor & Control as a field of activity that accompanies all four phases from beginning to end.

### What does the Project Manager work with?

Above all with the Project Work Plan as the baseline, with logs for risks, issues, decisions and changes, and with status and progress reports to the Project Steering Committee.

## Related terms

- [Project Manager](https://pmdecoder.com/en/glossary/project-manager-pm2/)
- [Control](https://pmdecoder.com/en/glossary/control/)
- [Corrective action](https://pmdecoder.com/en/glossary/corrective-action/)
- [Project Progress Report](https://pmdecoder.com/en/glossary/project-progress-report/)
- [Change control](https://pmdecoder.com/en/glossary/change-control/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.