# Milestone schedule

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Overview of key project events](https://pmdecoder.com/en/concept/overview-of-key-project-events/)
- Topic area: [Scheduling](https://pmdecoder.com/en/area/scheduling/)
- Canonical version: https://pmdecoder.com/en/glossary/milestone-schedule/

## Definition

In PMI usage, a milestone schedule is a schedule that shows only the milestones of a project together with their planned dates. It omits individual activities and condenses the plan to the events that matter to the sponsor, management and other stakeholders. A high-level milestone schedule is often produced as early as the project charter, before a detailed schedule exists. Later it is derived from the detailed schedule and serves as an overview in reports.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Milestone plan](https://pmdecoder.com/en/glossary/milestone-plan/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Classification

- Broader term: [Project schedule](https://pmdecoder.com/en/glossary/project-schedule-pmi/)

## Distinction

The cross-framework milestone plan refers to the same thing. The complete project schedule contains all activities with durations and dependencies, the milestone schedule only the events. A roadmap usually extends beyond a single project and is scheduled less bindingly.

## In practice

The management of a machine builder wants to see the status of the development of a new product line on a single page. The project office therefore produces a milestone schedule with eight events, from the concept decision to the start of series production, each with its planned and forecast date. A traffic light shows that certification is at risk; the details can be found in the underlying schedule.

## Frequently asked questions

### Who is a milestone schedule intended for?

Mainly for people who need an overview of the project but not every activity, such as the sponsor, the steering committee or customers. The project team works with the detailed plan.

### Can a milestone schedule replace the detailed schedule?

Sometimes in very small undertakings. As a rule it cannot, because without activities and dependencies it is impossible to tell whether the dates are realistic and which work puts them at risk.

## Related terms

- [Milestone plan](https://pmdecoder.com/en/glossary/milestone-plan/)
- [Milestone](https://pmdecoder.com/en/glossary/milestone-pmi/)
- [Project schedule](https://pmdecoder.com/en/glossary/project-schedule-pmi/)
- [Gantt chart](https://pmdecoder.com/en/glossary/gantt-chart-pmi/)
- [Roadmap](https://pmdecoder.com/en/glossary/roadmap/)

---