# Milestone

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Significant event in the course of a project](https://pmdecoder.com/en/concept/significant-event-in-the-course-of-a-project/)
- Topic area: [Scheduling](https://pmdecoder.com/en/area/scheduling/)
- Canonical version: https://pmdecoder.com/en/glossary/milestone-pmi/

## Definition

In PMI usage, a milestone is a notable point in time or event in a project, a programme or a portfolio. In the schedule it has zero duration, because it does not represent work but marks that something has been achieved, such as the completion of a deliverable, an acceptance or a decision. Milestones can be set by the sponsor or by contract, or defined by the team on the basis of historical experience. They are kept in a separate list and serve as reference points for reporting and control.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Milestone](https://pmdecoder.com/en/glossary/milestone/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The milestone as defined in ISO 21506 refers to the same thing; this entry gives the PMI view. An activity has a duration, a milestone does not. A phase gate is a decision point at the end of a phase and often coincides with a milestone, but is characterized by the decision on whether to proceed.

## In practice

In a project to introduce new HR software, the project manager sets five milestones: contract signed, configuration accepted, data migration tested, pilot area live and roll-out completed. The milestone “Configuration accepted” only counts as reached once the HR department has signed the acceptance record, not merely when the configuration has been set up.

## Frequently asked questions

### How many milestones does a project need?

Enough to make progress visible at sensible intervals, but few enough for each one to be meaningful in its own right. A milestone for every detail dilutes their value.

### How should a milestone be worded?

As a state that has been reached, such as “Prototype accepted”, with a clear criterion for recognizing that it has been achieved. Wording such as “Work on prototype” describes an activity, not a milestone.

## Related terms

- [Milestone](https://pmdecoder.com/en/glossary/milestone/)
- [Milestone schedule](https://pmdecoder.com/en/glossary/milestone-schedule/)
- [Activity](https://pmdecoder.com/en/glossary/activity-pmi/)
- [Phase gate](https://pmdecoder.com/en/glossary/phase-gate-pmi/)
- [Project schedule](https://pmdecoder.com/en/glossary/project-schedule-pmi/)

---