# Milestone plan

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Overview of key project events](https://pmdecoder.com/en/concept/overview-of-key-project-events/)
- Topic area: [Scheduling](https://pmdecoder.com/en/area/scheduling/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/milestone-plan/

## Definition

A milestone plan lists the key events of a project, such as project start, completion of the concept phase, approval, completion of prototypes, commissioning and acceptance. Each milestone has a date, an unambiguous description of the state that must have been reached by then and often a person responsible. Because it does without activities and bars, it is particularly suitable for sponsors and governance bodies.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Milestone schedule](https://pmdecoder.com/en/glossary/milestone-schedule/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

A milestone is a single event; the milestone plan is the overview of all milestones. Unlike the high-level schedule, it contains no periods, only points in time. Milestone trend analysis builds on it and tracks how the expected dates shift over time.

## In practice

A start-up is developing a device for water analysis and reports regularly to its investors on progress. The milestone plan comprises nine points, from a working laboratory model through certification to the first series delivery. For each one, it is specified how it will be recognized: the laboratory model only counts as achieved when it passes three defined series of measurements without failure. This avoids discussions about milestones that have been half reached.

## Frequently asked questions

### How many milestones should a plan contain?

Enough to check progress at sensible intervals, which for most projects means between five and fifteen. Too many milestones dilute their significance.

### How do you recognize a well-formulated milestone?

It describes a verifiable state, not an activity: “Building permit granted” rather than “Apply for permit”.

## Related terms

- [Milestone](https://pmdecoder.com/en/glossary/milestone/)
- [High-level schedule](https://pmdecoder.com/en/glossary/high-level-schedule/)
- [Trend analysis](https://pmdecoder.com/en/glossary/trend-analysis/)
- [Project schedule](https://pmdecoder.com/en/glossary/project-schedule/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.