# Meeting minutes

also: Minutes of meeting

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Topic area: [Stakeholders and communication](https://pmdecoder.com/en/area/stakeholders-and-communication/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/meeting-minutes/

## Definition

Meeting minutes record what was discussed and decided in a meeting. Particularly important for projects are the decisions and the agreed actions with owners and due dates. Action minutes note only the results, whereas narrative minutes also reflect the course of the discussion. The minutes are distributed promptly and are deemed accepted if nobody objects within an agreed period.

## Equivalents in other frameworks

No equivalents have been recorded for this term yet.

## Other terms

- Minutes of meeting (synonym)
- Action minutes (related, not equivalent)

## Distinction

Minutes document a single meeting, whereas an issue list tracks topics across many meetings. In everyday project work, running records are sometimes also called minutes (Protokoll in German), such as a change or decision record; what is meant then is a log, that is, a chronological list of entries. The construction diary (Bautagebuch) is a special form of daily record on construction sites.

## In practice

In a project involving several design firms, a dispute arises over whether the location of a plant room had already been decided. The action minutes of the design meeting six weeks earlier contain the decision with date and names, and nobody had objected. The dispute is settled in ten minutes. Since then, every meeting ends with the decisions being read out so that any ambiguities are noticed immediately.

## Frequently asked questions

### What belongs in action minutes?

Date, participants, agenda items, decisions, actions with owners and due dates, and the date of the next meeting.

### Who takes the minutes?

A designated person or a rotating role. The project manager should not have to take them if they are also chairing the meeting.

## Related terms

- [Issue](https://pmdecoder.com/en/glossary/issue/)
- [Project communication](https://pmdecoder.com/en/glossary/project-communication/)

---