# Matrix organization

also: Matrix structure

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Organization structure with dual reporting](https://pmdecoder.com/en/concept/organization-structure-with-dual-reporting/)
- Topic area: [Project organization](https://pmdecoder.com/en/area/project-organization/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/matrix-organization/

## Definition

In a matrix organization, two management dimensions overlap: the permanent structure by functions or divisions and the temporary structure by projects. The project manager determines what is to be done in the project and when; the line managers decide who does it and how the specialist work is carried out. Depending on which side is stronger, one speaks of a weak, balanced or strong matrix.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Matrix organization](https://pmdecoder.com/en/glossary/matrix-organization-pmi/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

Unlike the line organization, there are two lines of instruction, which calls for explicit rules for conflicts. In the pure project organization, staff are removed from the line entirely for the duration of the project; in the matrix they remain attached to their department. The influence project organization, in which the project manager only coordinates, is regarded as the weakest form.

## In practice

An automotive supplier develops a new braking system in a strong matrix. The project manager controls budget and schedule, while the developers continue to belong to the electronics department. When the department wants to withdraw a colleague at short notice to deal with a customer problem, a rule agreed in advance applies: withdrawals of more than two days are agreed with the project manager and, if there is disagreement, decided by the steering committee.

## Frequently asked questions

### Why is the matrix organization considered prone to conflict?

Because staff have two superiors whose priorities may diverge. Without clear escalation rules, the conflict is fought out at the expense of the employees.

### When does a matrix make sense?

When many projects run in parallel that need expertise from several departments, and specialists are not to be removed from their department permanently.

## Related terms

- [Line organization](https://pmdecoder.com/en/glossary/line-organization/)
- [Project manager](https://pmdecoder.com/en/glossary/project-manager/)
- [Line manager](https://pmdecoder.com/en/glossary/line-manager/)
- [Project-oriented organization](https://pmdecoder.com/en/glossary/project-oriented-organization/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.