# Managing product delivery

- Framework: [PRINCE2](https://pmdecoder.com/en/framework/prince2/)
- Reference: PRINCE2 7, Prozesse
- Edition: PRINCE2 7
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/managing-product-delivery/

## Definition

Managing product delivery governs the interface in PRINCE2 between the project manager and the teams that create the products. It is the responsibility of the Team Manager, or of the project manager on small projects. The process has three steps: a work package is accepted once scope, quality requirements, dates and tolerances have been clarified; it is then executed, with the team reporting progress and carrying out quality checks; and finally the completed and approved products are delivered. The process does not prescribe how the team works internally, whether agile or traditional.

## Equivalents in other frameworks

No equivalents have been recorded for this term yet.

## Distinction

Controlling a stage describes the project manager’s view, managing product delivery the view of the delivery teams. The process is not a technical method for development or construction; it only governs how work is agreed, tracked and handed over. Work packages are thus the link between the two levels.

## In practice

An external service provider receives the work package to build the interface between accounting and the online shop. The Team Manager first reviews the requirements and agrees a tolerance of two weeks. The team works in short iterations, reports progress weekly and delivers the interface once it has passed testing.

## Frequently asked questions

### Does a supplier need to know PRINCE2 to use this process?

No. What matters is that work packages are clearly agreed, progress is reported and products are delivered after checking. The supplier’s internal way of working is its own concern.

### What happens if a team is about to exceed its tolerance?

The Team Manager informs the project manager, who decides within their own tolerances or escalates further to the Project Board.

## Related terms

- [Team Manager](https://pmdecoder.com/en/glossary/team-manager/)
- [Controlling a stage](https://pmdecoder.com/en/glossary/controlling-a-stage/)
- [Focus on products principle](https://pmdecoder.com/en/glossary/focus-on-products-principle/)
- [Work package](https://pmdecoder.com/en/glossary/work-package/)
- [Work package](https://pmdecoder.com/en/glossary/work-package-pmi/)
- [Work Package](https://pmdecoder.com/en/glossary/work-package-prince2/)
- [Team Plan](https://pmdecoder.com/en/glossary/team-plan/)
- [Checkpoint Report](https://pmdecoder.com/en/glossary/checkpoint-report/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.