# Management Stage

- Framework: [PRINCE2](https://pmdecoder.com/en/framework/prince2/)
- Reference: PRINCE2 7, Praktik Pläne
- Edition: PRINCE2 7
- Concept: [Defined stage of a project](https://pmdecoder.com/en/concept/defined-stage-of-a-project/)
- Topic area: [Fundamentals](https://pmdecoder.com/en/area/fundamentals/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/management-stage/

## Definition

A management stage in PRINCE2 is a section of the project that is authorized by the Project Board and managed by the Project Manager within agreed tolerances. Each stage has its own detailed plan. At its end, the Project Board decides whether the project continues, is adjusted or is closed. Management stages follow one another and do not overlap. The first is always the initiation stage, followed by at least one more. Their number and length depend on risk, complexity and the points at which decisions make sense.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Project phase](https://pmdecoder.com/en/glossary/project-phase/) | closely related | A unit of authorization and direction that need not match technical stages. |
| PMI / PMBOK Guide | [Project phase](https://pmdecoder.com/en/glossary/project-phase-pmi/) | closely related | A unit of authorization and direction that need not match technical stages. |

## Distinction

Project phases in ISO 21506 or PMI publications are often defined by the type of work, such as concept, implementation and roll-out. PRINCE2 explicitly distinguishes technical stages, which may overlap, from management stages as units of authorization. The two may coincide but need not; a technical activity can run across a stage boundary.

## In practice

A software project is divided technically into analysis, development, testing and roll-out, which partly overlap. For control purposes the Project Board defines three management stages: initiation, a stage up to the first production release and a stage up to the completion of roll-out. At the end of each stage it reassesses costs, benefits and risks.

## Frequently asked questions

### How many management stages does a project need?

At least two: initiation and one further stage. More stages mean more control, but also more effort for planning and authorization.

### May management stages overlap?

No. They follow one another without gaps, so that it is always clear which plan and which tolerances apply.

## Related terms

- [Manage by stages](https://pmdecoder.com/en/glossary/manage-by-stages/)
- [Managing a stage boundary](https://pmdecoder.com/en/glossary/managing-a-stage-boundary/)
- [Project phase](https://pmdecoder.com/en/glossary/project-phase/)
- [Project phase](https://pmdecoder.com/en/glossary/project-phase-pmi/)
- [Gate](https://pmdecoder.com/en/glossary/gate/)
- [Stage Plan](https://pmdecoder.com/en/glossary/stage-plan/)
- [End Stage Report](https://pmdecoder.com/en/glossary/end-stage-report/)
- [Controlling a stage](https://pmdecoder.com/en/glossary/controlling-a-stage/)

---