# Management reserve

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Reserve for unforeseen work](https://pmdecoder.com/en/concept/reserve-for-unforeseen-work/)
- Topic area: [Risks and opportunities](https://pmdecoder.com/en/area/risks-and-opportunities/)
- Canonical version: https://pmdecoder.com/en/glossary/management-reserve-pmi/

## Definition

In PMI usage, the management reserve is an amount of money or time withheld outside the performance measurement baseline for management control purposes. It is intended for work that belongs to the project scope but could not be foreseen during planning, the so-called unknown unknowns. The reserve is part of the project budget but not of the cost baseline. Its use is usually decided not by the project manager alone but by a higher authority such as the sponsor or a steering body. When a portion is released, it moves into the baseline through change control. Organizations often set the amount as a flat rate, depending on the novelty and complexity of the undertaking.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Management reserve](https://pmdecoder.com/en/glossary/management-reserve/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The management reserve corresponds to the Managementreserve of ISO 21506. The distinction from the contingency reserve is essential: the latter covers identified risks, is part of the baseline and is managed by the project manager. A budget increase for additional scope, on the other hand, is not a matter for the management reserve but an approved change.

## In practice

During the introduction of a new point-of-sale system, it turns out that an interface to the parent company’s merchandise management system works differently from its documentation. The adjustment costs 60,000 euros and was not covered by any risk. The project manager applies to the sponsor for release from the management reserve. Once approved, the amount is transferred into the cost baseline through a change request.

## Frequently asked questions

### Is the management reserve part of earned value calculations?

No. As long as it has not been released, it lies outside the performance measurement baseline and is not included in planned value or budget at completion. Only after release does it become part of the baseline.

### May the management reserve be used for new requirements?

Not in the proper sense. It covers unforeseen work within the agreed scope. New requirements extend the scope and need their own approval, usually with additional budget.

## Related terms

- [Management reserve](https://pmdecoder.com/en/glossary/management-reserve/)
- [Contingency reserve](https://pmdecoder.com/en/glossary/contingency-reserve/)
- [Project budget](https://pmdecoder.com/en/glossary/project-budget-pmi/)
- [Performance measurement baseline](https://pmdecoder.com/en/glossary/performance-measurement-baseline-pmi/)
- [Change control](https://pmdecoder.com/en/glossary/change-control-pmi/)

---