# Manage by exception principle

- Framework: [PRINCE2](https://pmdecoder.com/en/framework/prince2/)
- Reference: PRINCE2 7, Grundprinzipien
- Edition: PRINCE2 7
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/manage-by-exception-principle/

## Definition

The manage by exception principle governs how authority is distributed between the levels of a PRINCE2 project. Each level sets objectives and tolerances for the level below, that is, permitted margins for aspects such as time, cost, scope or quality. As long as the forecast stays within those limits, the lower level works independently and reports at agreed intervals. If a tolerance is forecast to be exceeded, an exception exists and is escalated to the next level up. This relieves senior management, which only needs to deal with matters that genuinely require its decision.

## Equivalents in other frameworks

No equivalents have been recorded for this term yet.

## Distinction

Management by exception in general business administration describes the same basic idea. PRINCE2 makes it binding and links it to defined tolerances, reports and levels. Deviations within tolerance are not yet an exception; the responsible level resolves them itself, for example through corrective action.

## In practice

For one stage of a software project, the Project Board approves 400,000 euros with a tolerance of ten per cent and an end date with two weeks of leeway. The project manager absorbs a one-week delay by replanning. When a supplier drops out and costs threaten to rise by 15 per cent, he informs the Project Board immediately and presents options.

## Frequently asked questions

### Does this mean the Project Board only hears about problems?

No. It receives regular progress reports and stays informed. It only has to make decisions when a tolerance is at risk or an authorization is due.

### Who sets the tolerances?

The level above in each case: the commissioning organization for the project, the Project Board for the stages, and the project manager for work packages.

## Related terms

- [Tolerance (PRINCE2)](https://pmdecoder.com/en/glossary/tolerance-prince2/)
- [Exception (PRINCE2)](https://pmdecoder.com/en/glossary/exception-prince2/)
- [Project Board](https://pmdecoder.com/en/glossary/project-board/)
- [Variance threshold](https://pmdecoder.com/en/glossary/variance-threshold/)
- [Variance](https://pmdecoder.com/en/glossary/variance/)
- [Exception Report](https://pmdecoder.com/en/glossary/exception-report/)
- [Exception Plan](https://pmdecoder.com/en/glossary/exception-plan/)
- [Directing a project](https://pmdecoder.com/en/glossary/directing-a-project/)

---