# Logical relationship

also: Precedence relationship

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Scheduling dependency between two activities](https://pmdecoder.com/en/concept/scheduling-dependency-between-two-activities/)
- Topic area: [Network planning](https://pmdecoder.com/en/area/network-planning/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/logical-relationship/

## Definition

A logical relationship links a predecessor to a successor and specifies which point in time of the one is tied to which point in time of the other. There are four types: finish-to-start, start-to-start, finish-to-finish and start-to-finish. In addition, a time interval can be specified to express a waiting period or an overlap.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Logical relationship](https://pmdecoder.com/en/glossary/logical-relationship-pmi/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Classification

- Narrower terms: [Start-to-start relationship](https://pmdecoder.com/en/glossary/start-to-start-relationship/), [Finish-to-finish relationship](https://pmdecoder.com/en/glossary/finish-to-finish-relationship/), [Finish-to-start relationship](https://pmdecoder.com/en/glossary/finish-to-start-relationship/), [Start-to-finish relationship](https://pmdecoder.com/en/glossary/start-to-finish-relationship/)

## Distinction

A dependency describes the underlying reason why activities are connected; the logical relationship is its formal representation in the network schedule. A date constraint ties an activity to a calendar date, not to another activity. In German, the four types are known as Normalfolge, Anfangsfolge, Endfolge and Sprungfolge.

## In practice

When a library moves, the planner specifies that packing a stack room must be complete before its transport begins. Setting up the shelves at the new site is to start at the same time as dismantling them at the old one. And the handover of the old building may only finish once cleaning is also complete. These three types of relationship are enough to represent the entire move; a fourth is not needed.

## Frequently asked questions

### Which logical relationship is the most common?

Finish-to-start. In most schedules it accounts for by far the largest share of links.

### What is a time interval in a logical relationship?

A period that must lie between the linked points in time. A positive value means a waiting period, a negative value a permitted overlap.

## Related terms

- [Finish-to-start relationship](https://pmdecoder.com/en/glossary/finish-to-start-relationship/)
- [Start-to-start relationship](https://pmdecoder.com/en/glossary/start-to-start-relationship/)
- [Finish-to-finish relationship](https://pmdecoder.com/en/glossary/finish-to-finish-relationship/)
- [Start-to-finish relationship](https://pmdecoder.com/en/glossary/start-to-finish-relationship/)
- [Dependency](https://pmdecoder.com/en/glossary/dependency/)
- [Lead](https://pmdecoder.com/en/glossary/lead/)

---