# Logical relationship

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Scheduling dependency between two activities](https://pmdecoder.com/en/concept/scheduling-dependency-between-two-activities/)
- Topic area: [Network planning](https://pmdecoder.com/en/area/network-planning/)
- Canonical version: https://pmdecoder.com/en/glossary/logical-relationship-pmi/

## Definition

A logical relationship connects two activities, or an activity and a milestone, in a schedule and defines how their dates depend on each other. PMI distinguishes four types: finish-to-start, finish-to-finish, start-to-start and start-to-finish. Each relationship has a predecessor and a successor and can be supplemented by a lag or lead. Taken together, these relationships form the logic of the schedule on which the forward pass and backward pass are based. Missing or incorrect relationships lead to unreliable dates.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Logical relationship](https://pmdecoder.com/en/glossary/logical-relationship/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Classification

- Narrower terms: [Finish-to-finish](https://pmdecoder.com/en/glossary/finish-to-finish/), [Finish-to-start](https://pmdecoder.com/en/glossary/finish-to-start/), [Start-to-finish](https://pmdecoder.com/en/glossary/start-to-finish/), [Start-to-start](https://pmdecoder.com/en/glossary/start-to-start/)

## Distinction

The logical relationship corresponds to the German Anordnungsbeziehung in network planning. In the PMI context, a further distinction is made according to the origin of a dependency, for example mandatory by nature of the work or discretionary, internal or external. That describes the reason for the dependency, whereas the logical relationship describes its form in the schedule.

## In practice

When building a new customer portal, the project manager checks before the first schedule calculation that every activity has at least one predecessor and one successor. She notices that the data protection review is floating freely in the plan. It is linked as a predecessor of go-live, and the calculated launch date immediately moves by a week.

## Frequently asked questions

### Why should every activity have a predecessor and a successor?

Otherwise delays cannot be passed through the network, and the plan shows an end date that is too optimistic. The only exceptions are the project start and the project end.

### Which relationship type is most common?

Finish-to-start. Start-to-start and finish-to-finish occur with overlapping work; start-to-finish is rare.

## Related terms

- [Logical relationship](https://pmdecoder.com/en/glossary/logical-relationship/)
- [Finish-to-start](https://pmdecoder.com/en/glossary/finish-to-start/)
- [Predecessor activity](https://pmdecoder.com/en/glossary/predecessor-activity-pmi/)
- [Successor activity](https://pmdecoder.com/en/glossary/successor-activity-pmi/)
- [Precedence diagramming method](https://pmdecoder.com/en/glossary/precedence-diagramming-method/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.