# Line organization

also: Line structure

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Organization structure with single line of authority](https://pmdecoder.com/en/concept/organization-structure-with-single-line-of-authority/)
- Topic area: [Project organization](https://pmdecoder.com/en/area/project-organization/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/line-organization/

## Definition

In a line organization, positions are arranged hierarchically so that each receives instructions from only one higher authority. Information and decisions follow the chain of command from top to bottom and back again. The form is based on the principle of unity of command and is widespread in functionally structured companies.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Functional organization](https://pmdecoder.com/en/glossary/functional-organization/) | closely related | emphasizes the division by specialist functions, the line organization the simple chain of command |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

For projects, the line organization is the opposite pole to the pure project organization: projects run within the existing departments, and a project manager with authority to give instructions is often missing or weak. The matrix organization combines both principles by assigning staff to a line and a project at the same time. The line-and-staff organization adds advisory staff positions without authority to give instructions to the line.

## In practice

A trade business with master craftsmen in charge of electrical, plumbing and heating work handles customer orders within the line. On a school building project in which all trades have to work closely together, this form reaches its limits: coordination runs through three master craftsmen and the managing director and takes too long. The business therefore appoints a project manager for this undertaking who is allowed to coordinate across areas.

## Frequently asked questions

### What advantages does a line organization offer for projects?

Clear responsibilities and unambiguous lines of instruction; in addition, the professional home of those involved remains untouched.

### What are its disadvantages?

Long decision paths, departmental thinking and a lack of overall responsibility make projects that affect several areas more difficult.

## Related terms

- [Matrix organization](https://pmdecoder.com/en/glossary/matrix-organization/)
- [Project-oriented organization](https://pmdecoder.com/en/glossary/project-oriented-organization/)
- [Line manager](https://pmdecoder.com/en/glossary/line-manager/)
- [Organization chart](https://pmdecoder.com/en/glossary/organization-chart/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.